Decison package_Noosa Chocolate Factory

Attached to the e-mail MCU16/0098 & OPW16/0183 - Request to change existing approval - 21 Venture Drive NOOSAVILLE.

of 40

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 11, section 1. The text section number identifies this passage in the reader.

Noosa Council documents




                                                                                                         MCU16/0098


                      60.     Prior to the completion of the development and commencement of use, all site
                              surfaces must be effectively stabilised using methods which have achieved
                              effective short-term stabilisation and which will continue to achieve effective
                              stabilisation in the medium to long-term. For the purpose of this condition, an
                              effectively stabilised surface is defined as one that does not, or is not likely to
                              result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to
                              sedimentation, or lead to water contamination.
                              Damage to Services and Assets
                      61.     Any damage caused to existing services, streetscape and assets (including kerb
                              and footpath) as a result of the development works must be repaired at no cost to
                              the asset owner at the following times:
                              a.       Where the damage would cause a hazard to pedestrian or vehicle safety,
                                       immediately; or
                              b.       Where otherwise, upon completion of the works associated with the
                                       development.
                              Any repair work which proposes to alter the alignment or level of existing services
                              and assets must first be referred to the relevant service authority for approval.
                              FOLLOWING CONSTRUCTION
                              Certification
                      62.     Upon completion of the work and prior to the final inspection a certificate must be
                              issued by an RPEQ certifying that the works have been constructed in accordance
                              with the Operational Works permit and applicable engineering standards.
                      63.     A final inspection and approval of the completed works by Council’s Inspector is
                              required. Please contact Council on 5329 6244 to arrange for the inspection
                      5       REFERRAL AGENCIES

                      Not Applicable.
                      6       ADVISORY NOTES

                      The following notes are included for guidance and information purposes only and do not
                      form part of the assessment manager conditions:
                      PLANNING
                              Aboriginal Cultural Heritage Act 2003
                      1.      There may be a requirement to establish a Cultural Heritage Management Plan
                              and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003
                              (ACH Act).
                              The ACH Act establishes a cultural heritage duty of care which provides that: “A
                              person who carries out an activity must take all reasonable and practicable
                              measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an
                              offence to fail to comply with the duty of care. Substantial monetary penalties may
                              apply to individuals or corporations breaching this duty of care. Injunctions may
                              also be issued by the Land and Resources Tribunal, and the Minister administering
                              the ACH Act can also issue stop orders for an activity that is harming or is likely to
                              harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural
                              heritage.




                                                                                                             Page 11 of 18


Document Set ID: 20204040
Version: 1, Version Date: 22/11/2016                                                                 Print Date: 22 November 2016, 1:58 PM
Log in to download the original file

Decison package_Noosa Chocolate Factory.pdf · 3.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.