Noosa Council documents




                                                                                                        MCU16/0098


                              You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any
                              obligations under the ACH Act.
                              Equitable Access and Facilities
                      2.      The plans for the proposed building work have NOT been assessed for compliance
                              with the requirements of the National Construction Code - Building Code of
                              Australia (Volume 1) as they relate to people with disabilities. Your attention is
                              also directed to the fact that in addition to the requirements of the National
                              Construction Code as they relate to people with disabilities, one or more of the
                              following may impact on the proposed building work:
                              a.       the Disability Discrimination Act 1992 (Commonwealth);
                              b.       the Anti-Discrimination Act 1991 (Queensland); and
                              c.       the Disability (Access to Premises – Buildings) Standards.
                              Development Compliance Inspection
                      3.      Prior to the commencement of the use, please contact Council's DA Planning
                              Section to arrange a Development Compliance Inspection.
                              Infrastructure Charges
                      4.      This Development Permit will trigger an “Infrastructure Charge Notice” to be issued
                              in accordance with Council’s “Charges Resolution” made pursuant to the
                              Sustainable Planning Act 2009 and in conjunction with the State Planning
                              Regulatory Provision (Adopted Charges).
                              ENGINEERING
                              General Advisory Notes
                      5.      Council has undertaken an audit check of the Operational Works drawings in
                              relations to the proposed works. A detailed check of the calculations and drawings
                              has not been undertaken, as they have been certified by a RPEQ. The RPEQ
                              bears full responsibility for all aspects of the engineering design. Council reserves
                              the right to require further amendments and/or additions at a later date should
                              design errors become apparent.
                      6.      Council reserves the right to call up any performance bond held or levy charges
                              against the property, should emergency works be required to be undertaken by
                              Council to make the site safe due to inactivity on the development site for extended
                              periods of time.
                      7.      Amendments to plans, in accordance to the relevant conditions, and/or any
                              requested changes to the conditions of this decision notice must be made within
                              the appeal period or the suspended/extended appeal period. Alternatively, an
                              application for “Request to change an existing approval” under the Sustainable
                              Planning Act 2009 must be made along with Council’s applicable fees.
                      8.      It should be noted prior to arranging a pre-start meeting the Right of Appeal Period
                              of 20 business days should have been passed or the applicant has have confirmed
                              by a letter or an email that he/she has accepted the conditions of Decision Notice
                              and waived his/her appeal right.




                                                                                                            Page 12 of 18


Document Set ID: 20204040
Version: 1, Version Date: 22/11/2016                                                                Print Date: 22 November 2016, 1:58 PM
Log in to download the original file

Decison package_Noosa Chocolate Factory.pdf · 3.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.