MCU16/0098
Erosion and Sediment Control
9. Accepted best practice standards include:
a. the Sunshine Coast Regional Council Manual for Erosion and Sediment
Control V1.2 or other superseding document subsequently adopted by
Council;
b. Best Practice Erosion and Sediment Control, International Erosion Control
Association (2008)
10. As a general rule, a site is determined to have achieved effective short-term
stabilisation if at the completion of the works:
a. Methods of stabilisation are:
i. appropriate for slopes and slope lengths; and
ii. are consistent with best practice environmental management practices
such as in the Manual for Erosion and Sediment Control or the IECA
Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in
visible evidence of sedimentation or erosion, or lead to water contamination.
c. If at the time of the completion of the works, the method of short-term
stabilisation has not achieved a level of stability that Council's Officers
believe will have a high probability of achieving long term stability, Council
Officers may take the following matters into consideration in determining
whether the site is capable of achieving medium to long-term stability:
d. Evidence that the site has been effectively stabilised in the short term;
e. Evidence that soil has been adequately ameliorated;
f. Evidence that seed of annual and perennial grass species has been applied
at an adequate rate; and
g. That grass seed has germinated at a density that is likely to achieve an
effective grass cover.
ENVIRONMENTAL HEALTH
Environmental Protection Act
11. It is a requirement of the Environmental Protection Act 1994 that if an owner or
occupier of land becomes aware that a Notifiable Activity (as defined by Schedule
2 of the Environmental Protection Act 1994) is being carried out on the land, or that
the land has been affected by a hazardous contaminant, they must, within 30 days
after becoming so aware, give notice to the Department of Environment &
Resource Management’s Contaminated Land Unit.
12. A person must not carry out any activity that causes, or is likely to cause,
environmental harm unless the person takes all reasonable and practicable
measures to prevent or minimise the harm. Environmental harm is defined as any
adverse effect, or potential adverse effect whether temporary or permanent and of
whatever magnitude, duration or frequency on an environmental value and
includes environmental nuisance.
Page 13 of 18
Document Set ID: 20204040
Version: 1, Version Date: 22/11/2016 Print Date: 22 November 2016, 1:58 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.