Decison package_Noosa Chocolate Factory
Attached to the e-mail MCU16/0098 & OPW16/0183 - Request to change existing approval - 21 Venture Drive NOOSAVILLE.
Original PDF page 7, section 1. The text section number identifies this passage in the reader.
Noosa Council documents
MCU16/0098
b. Proposed dates for commencement and completion of construction.
36. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible
to ensure that any subcontractors also have the appropriate insurance and public
liability documentation. Certificates demonstrating currency of public liability
insurance and works insurance covering the works must be submitted to Council
prior to the prestart meeting.
37. Council must be contacted at least 5 working days prior to any works commencing
to organise a prestart meeting*. The contact number to arrange a prestart meeting
is 5329 6244. The prestart meeting must include the relevant parties for the
following aspects of the works:
a. Civil engineering works.
b. Landscape works.
c. Erosion and sediment control works.
* (Refer to Advisory Note)
38. Copies of the approved plans, duly signed by the consultant Registered
Professional Engineer of Queensland (RPEQ) must be provided to Council’s
Engineering Officer Construction at the “prestart” meeting.
39. A detailed condition report including photographs of all frontages of the site must
be completed and submitted to Council prior to the prestart meeting.
40. A condition report including photographs of all fences and retaining walls bordering
the site and any buildings, structures, pathways, landscaping features etc on
adjoining properties that could potentially be impacted on by the proposed
earthworks and construction works must be completed and submitted to Council
prior to the prestart meeting.
41. A Construction Management Plan must be submitted to Council for approval prior
to the prestart meeting and must specifically include/address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of
Uniform Traffic Control Devices (MUTCD) detailing all temporary
signage and traffic control measures to be installed prior to
construction.
ii. Fencing to the work site during the construction phase to ensure the
safety of the public and the road users.
iii. Maintenance of safe pedestrians and cyclists access across the
frontage of the site both during daily construction and after daily
construction has ceased.
iv. Sufficient parking arrangements for trucks, machineries and
construction workers without adversely impacting on traffic flow and/or
the availability of on-street parking in the local street.
b. Maintenance and protection of water quality and existing drainage lines
through the construction site through the implementation of appropriate
erosion and sediment control measures.
Page 7 of 18
Document Set ID: 20204040
Version: 1, Version Date: 22/11/2016 Print Date: 22 November 2016, 1:58 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.