Attachment 3 - Construction Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Westcon Site Management Pty Ltd
o Limit the use of horns, bells, hooters or other audible signals on mobile equipment
to the maximum practicable extent, and where possible, fitting of warning lights,
rather than audible sirens or beepers;
o Implement regular inspection and maintenance schedules for all plant and
equipment;
o Avoid the use of air brakes on trucks in built up areas; and
4.9 Energy and raw materials management
Energy sources at the site are limited to grid-supplied electricity or fuel to operate
generators. Energy saving initiatives to be implemented will include turning off lights and
equipment when not in use. Lighting must not be operated at night. Where possible, energy
efficient plant is to be operated and building supplies are to be purchased. However it is
recognised that the selection of most building materials is provided by others.
Materials are to be purchased for construction only as required so that excess supplies are
not wasted.
4.10 Summary of General Activities
• Inducting and training new employees on the requirements of this section of the CMP;
• Managing waste activities;
• Managing site, plant and vehicle noise;
• Energy and raw material management
5.0 Fire Ant Management
5.1 If in a Fire Ant Restricted Area
• Visual check of site for any fire ant nests by a DPI fire ant officer.
• A Fire Ant Management Plan must be written for the site.
• All high risk activities must be undertaken in accordance with local regulations and in
consultation with DPI and local authorities.
5.2 If in a Non-restricted Area
• Visual check of site for any possible fire ant nests by selected subcontracted service
provider.
• Ensure no soil is taken from site or high risk activities are undertaken until area has
been inspected and no suspect ants detected.
• If suspect ants are detected identification is to be verified by a DPI fire ant officer prior
to undertaking and high risk activity.
• If fire ants are confirmed item 5.1 must apply.
Issue 2 July 1 Page 13