Attachment 3 - Construction Management Plan

of 17

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                      Westcon Site Management Pty Ltd



2.4 Site specific considerations

      The construction site, is located at 9 Ann Street, Noosaville, Qld, 4566

      The project is to undergo the following activities:

      Duplex - 2 x residences

3.0 General Requirements

3.1 Responsibilities

3.1.1 Project Manager
      The Director or Site Manager is responsible for daily management of site operations,
      supervision, administration and profitability of the facilities, monitoring of production
      costs and the management of plant maintenance in relation to this project.

          The Director or Site Manager is required to ensure that, before commencement of site
          activities, the CMP is developed to address the environmental protection of possible
          impacts and site-specific risks.

          The Director or Site Manager is required to ensure that:

           • Environmental protection requirements are implemented and adhered to throughout the
             site for contractors and employees.
           • Interfacing   and full co-operation with contractors, suppliers and authorities is
             maintained at all times.
           • Potential adverse environment impacts are assessed and monitoring of compliance with
             the CMP is conducted.
           • Environmental accidents, incidents and complaints on the site are reported, investigated
             and recommended actions implemented.
           • Environmental records are maintained.
           • Staff and subcontractors are assisted in identifying and implementation corrective
             actions as required.
           • Reviews of the operation of the CMP are conducted.




Issue 2              July 1                                                          Page 5
Log in to download the original file

Attachment 3 - Construction Management Plan.pdf · 259 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.