PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 7 MARCH 2017
7. A Construction Management Plan must be submitted to Council prior to the pre-start
meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and
traffic control measures prior to construction
ii. Maintenance of safe pedestrian access across the frontage of the site
both during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the
development
iv. Adequate parking arrangements for construction workers
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
b. Maintenance and protection of water quality and existing drainage lines through
the construction site through the implementation of appropriate erosion and
sediment control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic and services and other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
8. Any changes to the details associated with the supervising RPEQ or Principal
Contractor during construction, must be notified to council in writing within five
business days of the change occurring.
9. Any conflict between the development and an existing or proposed service must be
referred to the relevant service authority for determination prior to commencement of
works.
DURING CONSTRUCTION
Engineering
10. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets
must be repaired immediately where it creates a hazard to the community. In
circumstances where the damage does not create a hazard to the community, it must
be repaired immediately on completion of the works associated with the
development.
11. All works must be supervised by a Registered Professional Engineer of Queensland
(RPEQ) who is independent of the Developer and Principal Contractor, and they must
certify that all works conform to the Operational Works permit. Where municipal
works are involved, such confirmation must be submitted for the respective hold
points prior to any site inspection by Council Officers.
Page 11 of 91
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.