PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 7 MARCH 2017
31. Prior to the completion of the development, all site surfaces must be effectively
stabilised using methods which have achieved effective short-term stabilisation and
which will continue to achieve effective stabilisation in the medium to long-term (refer
to advisory notes). For the purpose of this condition, an effectively stabilised surface
is defined as one that does not, or is not likely to result in visible evidence of soil loss
caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water
contamination.
Damage to Services and Assets
32. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing services
and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION / PRIOR TO COMMENCEMENT OF USE
Certification
33. Upon completion of the work a certificate must be issued by an RPEQ certifying that
the works have been constructed in accordance with the Operational Works permit.
Landscaping
34. An amended landscaping plan must be submitted to Council for endorsement prior
the issue of a Development Permit for Building Works. The amended plan must
include in particular:
a. the works shown on the Approved Plans including a 2 metre wide planting bed
of native species suitable from screening the development to the Opal Street
and Diamond Lane frontage exclusive of the access driveway, generally
uncompromised by infrastructure items;
b. details of front boundary fencing along Diamond Lane and Opal Street;
c. Screening vegetation to the side boundary setback areas uncompromised by
infrastructure;
d. Species in accordance with Planning Scheme Policy 3 Landscape Plants and
Guidelines; and
e. Plans prepared by a landscape architect, landscape designer and/or
horticulturist with a minimum of 3 years current experience in the field of
landscape design.
35. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed to
grow to full form and be refurbished when its life expectancy is reached.
36. All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
Page 14 of 91
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.