Performance outcome                        Acceptable outcome                  Applicant response            Assessment
reasons                                    (b) subject to paragraph (c), a     lodgement discussions with
                                           sign erected or otherwise           MSQ.
                                           placed in position for              a) The aids to navigation
                                           prescribed tidal works is           are to be of a type
                                           integrated into the design and      consistent with standard
                                           construction of the works;          MSQ buoys and are
                                           (c) if a relevant planning scheme   therefore compatible with
                                           standard is more stringent          the character and amenity
                                           than the standard mentioned         of the works’ locality. SCG
                                           in paragraph (a) or (b)—the         has certified that the
                                           relevant planning scheme            signage is consistent with
                                           standard, to the extent it is       the requirements of the
                                           more stringent than the             Coastal Protection and
                                           standard mentioned in               Management Act.
                                           paragraph (a) or (b);               b) The dominance of the
                                           (d) any other relevant planning     signage will be based on
                                           scheme standard that is not         navigational safety
                                           inconsistent with the               requirements.
                                           standards mentioned in
                                           paragraphs (a), (b) and (c).
Earthwork, vegetation and rehabilitation
7.1 Excavation and filling for             The earthwork and filling for the   Not applicable.               The Project does not propose any
prescribed tidal works—                    prescribed tidal works is           The works do not include      excavation or filling therefore PO7.1
(a) is carried out only to the             consistent with each relevant       removal of any material,      is not applicable.
extent reasonably necessary                planning scheme standard.           excavation or filling.
for the works; and
(b) does not have a significant
adverse effect on—
(i) the natural features,
including the banks, of
the tidal water in the
works’ immediate
Log in to download the original file

2022-05-16 GC Agenda - Item 7 - Attachment 1 - Report from Marine Approval Specialists(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.