Performance outcome Acceptable outcome Applicant response Assessment
standard mentioned in
paragraph (a).
Design, construction and safety—jetties and piers
16.1 Prescribed tidal works that are a (s 5(2) outcome) Not applicable. The Project is not a jetty or pier
jetty or pier are designed and The design and construction of the Not a jetty or pier. therefore PO16.1 is not applicable.
constructed in a way to ensure jetty or pier is consistent with the
the jetty or pier is able to support following standards-
its intended loads, having regard (a) subject to paragraph (b), each
to its relevant loading matters. of the following Australian
Standards to the extent
requirements stated in the
Standard apply to relevant
loading matters for the design
or construction of the jetty or
pier—
(i) AS/NZS 1170.0;
(ii) AS/NZS 1170.1;
(iii) AS/NZS 1170.2;
(iv) AS 1170.4;
(v) AS 4997;
(b) if a relevant planning scheme
standard is more stringent
than the standard mentioned
in paragraph (a)—the
relevant planning scheme
standard, to the extent it is
more stringent than the
standard mentioned in
paragraph (a).
16.2 Prescribed tidal works that are a The design and construction of the The Project is not a jetty or pier
jetty or a pier are designed and jetty or pier is consistent with the therefore PO16.2 is not applicable.
constructed in a way to ensure following standards—
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.