Performance outcome Acceptable outcome Applicant response Assessment
around the pontoon, flotation unit to detach from
including tidal water the system for mooring the
affected by a flood or unit—
storm tide. (i) the standard applying
under paragraph (a); and
(ii) the pontoon’s flotation
unit is restrained with a
tethering system so that
it can withstand the
effects of the event;
(c) if a relevant planning scheme
standard is more stringent
than the standard mentioned
in paragraph (a) or (b)—the
relevant planning scheme
standard, to the extent it is
more stringent than the
standard mentioned in
paragraph (a) or (b).
18.5 Prescribed tidal works that are a The design and construction of the Not applicable. The Project is not a pontoon
pontoon identifies the lot to pontoon is consistent with the Not a pontoon. therefore PO18.5 is not applicable.
which the pontoon is connected. following standards—
(a) a label that identifies the lot
to which the pontoon is
connected is written or
stamped on, or fixed to, the
outside of the pontoon’s
flotation unit;
(b) if a relevant planning scheme
standard is more stringent
than the standard mentioned
in paragraph (a)—the
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.