SUPERSEDED - 05/1021 - COMPILED Decision Notice [As Published] · 132005.1021.02
NOOSA COUNCIL IDAS Development Application Decision Notice 7
The approved maintenance plan shall be incorporated in the Management Plan for the
development to ensure routine maintenance and a copy of this shall be provided for Council’s
records prior to commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
50. All site stormwater drainage shall be by means of a gravity system.
51. All stormwater drainage lines that will become Council property shall be inspected by closed circuit
television (CCTV) prior to commencement of the approved Use.
CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council
following satisfactory completion of construction works. The developer will be responsible for the
full cost of CCTV inspection, including any additional inspection necessary following defect
identification and rectification. This charge is payable prior to the issue of Operational Works
approval and will be determined on the unit rate basis current at the time of approval.
Sewer Mains
52. The existing sewer main that traverses the site shall be relocated generally in accordance with
Sewer Relocation Plan 05251/H1, dated July 2005, by Dryhurst Halstead Stuart Architects. To this
end, engineering plans and details of these works shall be prepared and submitted to Council for
approval prior to obtaining a Development Permit for Operational Works.
53. As required by Council's Water & Sewerage Section, the sewer relocation works shall also include
the existing residence connecting to the new sewer and the existing rising main from the residence
being abandoned.
54. The site shall be connected to Council’s sewerage reticulation systems and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
55. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
56. Each water connection to the water reticulation system shall extend to the property boundary and
be metered. All fees for the supply of water meters shall be paid to the Council.
Service Easements (Sewer)
57. A registered easement shall be created over the zone of influence of all sewers within the subject
site and over those parts of the subject site that are impacted upon by sewers on any adjoining
sites. The easements shall generally be parallel to and centred over the sewer main and be
equivalent in width to twice the depth to invert level of the sewer at the deepest point within the
allotment (measured from the finished surface) and be no less than 3.0m wide. All easements
shall be shown on any plans submitted for Operational Works / Building Works approval.
The Applicant’s Solicitor shall give Council’s Solicitor an appropriate undertaking in writing that the
Title Deed and the easement documents will be lodged at the Land Titles Office and any additional
Titles Office forms or requisitions requiring the consent of Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the use
commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
Redundant Easements
58. Any easements that are no longer required as a result of re-developing the site shall be
extinguished and removed from the title of the land.
Headworks Contributions
59. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28 and
PSP30 on Water Supply Headworks Contributions and Sewerage Headworks Contributions
respectively and at the rates applicable at the time of payment. An estimate only of the
contribution rates under the current policies is outlined below. These amounts will adjusted in line
with changes to the Consumer Price Index, All Groups Brisbane from December 2005 until the
date of payment.
Water Supply $7,725
Sewerage $8,494
ab c:\docume~1\abecker\locals~1\temp\bcl technologies\easypdf 5\@bcl@5c0dc6aa\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records