Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

16-001014-02A (Ultimate SCMMP)

Attached to the e-mail Operational Works Application OPW16/0203 - 4 of 4.

of 192

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (14.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

    4. Placing the components

    The chamber is supplied with inlet and outlet sides
    clearly marked and the pipe ends should be cut to suit.
    The position of the pipe centreline should be marked on
    both the pipe end and the chamber surface to ensure
    correct alignment relative to line and level through the
    HumeGard® GPT.


    It is important for the operation of the unit that the base
    of the unit remains level and square horizontally after
    positioning in the excavation. This should be carefully
    checked particularly in the case of two part chambers
    where dimensions of each part are measured before set
    out and lowering into the excavation.


    For two part chambers a sealed joint must be created
    between the bottom and top sections. This can be
    accomplished by placing either a mastic bead or a two
    part epoxy resin (either will be supplied), along the
    joint surface of the bottom component. The epoxy
    resin should be approximately 80 mm wide and at least
    6 mm thick.




    5. Initial backfill

    Once the main chamber is correctly positioned within
    the excavation, backfill the sides of the excavation with
    a suitable material to just below the inlet and outlet
    openings. This will create a safe working platform to
    enable the installation of the inlet and outlet pipes and
    fitting of rubber connectors (if supplied).




4   HumeGard® GPT
Log in to download the original file

16-001014-02A (Ultimate SCMMP).pdf · 14.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.