SAFETY IN DESIGN HAZARD REPORT
App? Action
Consideration Hazard / Comment Controlling Action Action By
Status
Method of excavation & plant requirements Conventional plant required for Contractor to ensure all works on-site Contractor Ongoing
excavation works comply the WH&S requirements and that
SWMS are prepared for each activity as
required.
Earthworks balances and location of stockpile spoil area for topsoil Contractor to ensure all works on-site Contractor Ongoing
material comply the WH&S requirements and that
SWMS are prepared for each activity as
required.
Depth of excavations Deep excavations for services Contractor to ensure all works on-site Contractor Ongoing
comply the WH&S requirements and that
SWMS are prepared for each activity as
required.
Adjacent properties affected by earthworks / Damage or injury to adjacent Contractor to ensure all works on-site Contractor Ongoing
excavations residents/unauthorised access to site. comply the WH&S requirements and that
SWMS are prepared for each activity as
required. Contractor to ensure that adjacent
properties are protected at all times during
construction. Site controls to be
implemented to avoid unauthorised access.
Road / Pavement / Carpark Design:
Road alignment and cross section
Pavement materials
Provision for pedestrians, cyclists, public
transport, heavy vehicles, emergency
vehicles, maintenance operations
Noise generation
Lighting
Crime prevention
Edge protections / guardrails / barriers
Drainage Conventional Comply to Standards Designer Complete
Document: QAF2024 Safety in Design Hazard Report – Generic
Revision 10 – 10/02/2015 Page 7 of 12
File: H:\B14\150-199\B14158.W\01 Final Layout Op Works\Checklists\B14158.W - Safety in Design_WQCP.docx [Update to show User's file] Calibre Consulting (Aust) Pty Ltd
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.