2.2 Construction phase drawdown management
Person Responsible ProponenUContractor
Management of groundwater intercepted during the course of excavation
below groundwater level throughout the Noosa on Weyba development.
To prevent or minimise impacts on existing groundwater conditions and on
receiving waters.
To maintain background conditions and prevent degradation to off-site
receiving environments.
To maintain background conditions and prevent impacts to sensitive
receptors such as vegetation communities and surface waters.
No discharge of groundwater intercepted during bulk earthworks or
construction of trenches, roads or stormwater treatment measures
without appropriate testing, and treatment if required.
No variation in groundwater levels and/or flow direction outside the site
boundary or in the immediate vicinity of sensitive receivers beyond the
effects of drought or flood.
Any groundwater encountered within areas of the site that contain acid
sulfate soils (ASS)shall be directed to appropriately located recharge
trenches to minimise drawdown and the potential oxidation of insitu
ASS.
Recharge trenches shall be implemented for excavations undertaken
in the vicinity of sensitive receiving environments (sensitive vegetation
communities and/or receiving waters). Recharge trenches shall be
located to mini mise the impacts of groundwater drawdown and any
associated impacts to water quality.
pH should be monitored weekly whilst dewatering to ensure waters are
compliant with the site’s release criteria, prior to discharge to the
recharge trench.
If additional storage volume is required, dewatered groundwater may
be pumped to a temporary sediment pond prior to being pumped to the
recharge trenches. No groundwater shall be discharged from the site
until the site’s water quality criteria are reached.
Reliable in situ monitoring equipment will be used for all monitoring.
This equipment will be calibrated at least fortnightly.
1 0838_GWMP_REH1 F.DOCX / NOOSA ON WEYBA / GWMP 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Part 17 of 37 Appendix 15 - Groundwater Assessment MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 60.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.