Attachment 15- Amended Water Supply and Sewerage Analysis MCU12/0208
Very large file (11.7 MB): the original may take a few minutes to open or download. The page text below is quick to read.
Noosa on Weyba
Water Supply and Sewerage Analysis
Table 6-4 NVL040 Ultimate Capacities
Required
Rising Velocity at Headloss
Design Design Single
Main Design at Design
Design PWWF Head Pump
Existing EP Diameter Flow Flow
Scenario power
(L/s) (m) (kW) (mm) (m/s) (m)
Ultimate 23,474 244.5 21.00 78 450 1.08 15.15
Ultimate
with
25,845 269 23.00 97 450 1.69 16.30
Developme
nt
6.3 Noosa on Weyba Network
An internal sewerage network to service the Noosa on Weyba development has been identified. It is noted
that in the SEQ Design and Construction Code, that a conventional system (i.e. gravity mains and pump
stations) are preferred over alternative strategies. However, with final lot configurations to be confirmed a
definitive internal network will be identified at a later date.
Alternative servicing strategies such as the use of low pressure sewers has been considered for this
development. For the purposes of this report a conventional system has been adopted, to demonstrate the
servicing strategy for conveyance from the site to the external network.
6.3.1 Gravity Mains
A network of gravity mains, ranging in size from 150 mm to 225 mm are required to service the development.
Analysis has indicated that the use of gravity mains at minimum grade will be able to service the
development.
Properties within Precinct 2 to the western edge are proposed to connect via 150 mm gravity mains to the
existing sewers along Lake Entrance Boulevard. The combined PWWF for these properties is 2.6L/s. The
existing development along Lake Entrance Boulevard currently discharging to the existing 150 mm gravity
main contribute approximately 4.6L/s at PWWF. The impact of these flows from the Noosa on Weyba
development on this network is expected to be minimal and maintain Unitywater’s DSS.
The reminder of the network in Precinct 1 will discharge to a central pump station servicing the development
and discharge it too the Unitywater pump stations SPSNV011. Details of the pump stations proposed to
service the Noosa on Weyba development is detailed in Section 6.4.
Development within the Precinct 1 (to the south of the site) may require multiple pump stations due to the
topography of the site and the configuration of the development area due to environmental constraints,
Details of the pump station capacities and discharge rising main is detailed in Table 6-5.
Northbrook Corporation Pty. Ltd. Version 4 17 September 2013
5101-19 Commercial in Confidence Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 15- Amended Water Supply and Sewerage Analysis MCU12/0208Related documentApplication case desk ↗
About this file
- File size
- 11.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.