                                               Noosa on Weyba Water Network Performance Assessment




4.2         Fire Flow Pressure Performance
The fire flow assessment for all options identified pressures at the development site and within NIDMA
are predicted to remain above the required pressure of 12 m during 2/3 maximum hour in the Ultimate
planning horizon. 2/3 maximum hour was determined to be at 7pm and is calculated from the maximum
flow into NIDMA.
Fire flow demands were assigned to all junctions within NIDMA to determine the critical fire flow
junction. Fire Flow demand was assigned to junctions as follows:
     •    Junctions with commercial demand      30 L/s.
     •    Junctions with residential demand     15 L/s.
The critical fire flow junction was found to be near the end of Traders Lane behind 118 Noosa-Eumundi
Road (refer to Figure 4-1). Residual pressure at this location without the inclusion of the proposed
development is predicted at fire flow demand at the hydrant to be 21.12 m. The addition of the
development site is predicted to reduce pressures at the critical point to a minimum of 13.38 m at
Ultimate. The model predicts that with the development the catchment will still meet the standards of
service.
Pressure results identified at 7pm during the fire flow performance assessment are provided below in
Table 4-2.
Table 4-2: 2038 Fire Flow Pressure Performance at 2/3 Maximum Hour

    Model                                     NOOSA_ON_WEYBA_        NOOSA_ON_WEYBA_C
  Junction ID          NTHWJ002350
                                                   CONN1                   ONN2

   Location /          Critical fire flow       Connection #1 at       Connection #2 at
  Description       junction within NIDMA     development boundary   development boundary

    Pressure
      Units                                        metres head

   Without
  Proposed                  21.12                           -                     -
 Development

    Option 1                13.99                     57.35                       -

    Option 2                13.38                     60.75                    55.42

    Option 3                14.41                     59.52                       -

 PASS / FAIL                PASS                     PASS                      PASS



4.3         Storage Assesment
The Noosa on Weyba development will be supplied from the Noosaville Industrial DMA. This DMA is
one of a number of DMAs dependent on the Tewantin Reservoirs for storage as shown in Figure 4-2
(Tewantin.




Status: Draft                                                                                        22/06/2012
Project number:                                    Page 6            Our ref: Noosa on Weyba WS Assessment.docx

Used in these records

About this file

File size
11.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 15- Amended Water Supply and Sewerage Analysis MCU12_0208.pdf · 11.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.