SPECIAL MEETING AGENDA 30 AUGUST 2021
Finance Risks Mitigation
Geotechnical conditions A detailed Geotechnical investigation report has been completed and the
give rise for contractor report provided as part of the tender documentation. Any required variations in
claiming variation costs. depth will be worked out by variation rates that have already been locked in
with the contractor as part of the contract specifications. A budget contingency
allows for this risk.
Subgrade material found Tender specifications specify clearly how and until what extent the existing
to be unsuitable for reuse subgrade material needs to be processed to reuse these materials. In case a
purposes within the certain amount is not found suitable, locked in rates are in place as part of the
projects. tender evaluation clarification process. A budget contingency allows for this
risk.
Clashes with public utility Prior tender phase, Council staff had extensive collaboration with Telstra to
provider Telstra give rise lock in the scope and timeframes. The contractor is aware of the requirements.
for contractor claiming The contractor will coordinate activities around these relocations.
variation costs.
Contingency amount This risk is mitigated through Council's highly experienced project team and
being insufficient. the appointment of an experienced contractor and contract supervision by an
experienced Superintendent. Any delay risks forthcoming of the current
pandemic is not included in the contingency amount. If contingency amount is
insufficient to cover the cost, this is to be mitigated by the budget approval
process.
Site access constraints Extensive research has been performed by the project team together with
give rise for contractor external consultants to make sure the bridges can be replaced using the
claiming variation cost. available access roads for SP1 as well as for SP2. Access constraints are well
embedded into the contract. A low residual risk is identified for SP2, captured
in the projects risk register and mitigation is budgeted into SP2’s project cost
estimate.
Program Risks Mitigation
There is the potential that Expected wet weather days are included in the tenderer's timeline.
the project is delayed due
to wet weather.
Resource risk. The contractor has nominated a capable team to undertake construction.
Construction takes longer The contractor is well resourced and has the available resources to deliver this
than allowed for. project successfully in conjunction with current works on hand. The use of
mainly precast materials such as concrete abutments, piers and deck units
reduce the risk of construction delays.
Lead time of materials Many associated risks are mitigated by ordering the materials as soon as
pushing the program out. possible after tender award. Especially the sheet piles required for Wahpunga
Lane bridge could have lead time issues, mainly due to the pandemic and
higher demand. The contractor is aware, manages this risk and works closely
together with Council's project team to minimise residual risk. As the sheet
piles are a key item in the construction, other options will be explored (e.g.,
alternative size of sheet pile with the same capacity and durability).
Safety Risks Mitigation
Site safety. The contractor has extensive experience with similar works and would be
appointed as the Principal Contractor responsible for all Workplace Health and
Safety of the site. Prior to construction commencing, workplace health and
safety and final traffic management plans will be required to be submitted to
Council for review. Regular audits on contractor compliance with these
approved plans will be undertaken by Council and WH&S teams throughout
construction.
Page 8 of 15