INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 31 MARCH 2015
Following lengthy delays in announcement of the funding, Council was eventually advised in
March 2015 that the funding application was unsuccessful.
As structural elements of the bridge are now urgent, this report aims to inform Council of the
rehabilitation options, the estimated costs involved and the extension to bridge life offered by the
various options.
Consulting engineers have informed Council that, as a minimum, the installation of an additional
column to each pier must be undertaken urgently this financial year.
2. Rehabilitation options
Based on the consulting engineer’s level 3 report, the below table describes the rehabilitation
options.
Budget option Description of works Timing Bridge life Cost
extended by
Option A) - Least • Installation of additional Required 2-4 years Approx.
initial cost columns to each pier immediately $200,000-
$250,000
Option B) - Works • Above plus; Columns 2-4 years Approx. $1.4M
to match current • Repair pilecap beams required
funded budget of • Encase piles immediately,
$1.4M • Cathodic protection to remainder of
pilecap beams works required
to be
completed in
2-4 years
Option C) - Full • Above plus; Columns 50 years Approx. $3.05M
scope, (partially • 60 pile encasements required (budget
funded) • deck waterproofing & immediately, shortfall of
scupper linings remainder of $1.65M)
• replace deck joints works required
• silane coatings to to be
pilecap beams, completed in
columns, headstocks, 2-4 years
abutments and deck
underside + sides
• clean up and coat all
stressing bar ends
• clean up and coat traffic
barriers & handrails
The Least Cost - Option A) of installing additional strengthening columns will alleviate the
immediate structural risk to the bridge however this option is only expected to give a few years
additional life to the bridge before more rehabilitation works are required.
The Intermediate Scope - Option B) is arbitrarily set to match the existing budget of $1.4Million
and also alleviates the immediate structural risk, however the remainder of the rehabilitation
works will also be required in a few years.
The Full Scope – Option C) allows the rehabilitation of the entire structure. This option allows all
risks to be dealt with as soon as possible under a single contract and under a single procurement
process. It is estimated that the full scope of works could be delivered in 6-9 months and likely to
span over the 14/15 and 15/16 financial years. The expected life of the bridge would be extended
by 50 years. This forms the basis of recommending that this is the preferred option and to carry
out the full scope of works and make the necessary budget adjustments.
Page 19 of 29