INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 31 MARCH 2015
6. CAPITAL PROGRAM DELIVERY STATUS - MARCH 2015
DOCUMENT INFORM AT ION
Author Asset Planning Coordinator, Bryan O’Connor
Planning & Infrastructure Department
Index ECM/Subject/2014-2015 Annual Capital Works Program
Attachments Nil
EXECUTIVE SUMMARY
The project delivery status report is presented quarterly to the Infrastructure and Services
Committee in order to provide an overall progress of the capital works program and allow
discussion of current projects being delivered. This report provides a general overview and
highlights the current and future activities of the projects being delivered.
This report is supported by the capital works program dashboard report which provides a brief
update for each project in terms of project description, budget, stage and target dates, as well as
highlighting any issues and comments with the delivery of the projects. A presentation of the
capital works program dashboard will be provided at the Infrastructure & Services Committee.
RECOMMENDATION
That Council note the report by the Asset Planning Coordinator to the Infrastructure & Services
Committee Meeting dated 31 March 2015 providing an update on the status of the projects being
delivered in the 2014/15 Capital Works Program.
REPORT
The purpose of this report is to inform the Infrastructure & Services Committee of the overall
status of the Capital Works Program projects to 9 March 2015. The report also provides an
opportunity to highlight individual projects within the program and also confirm the completion of
projects as they are being delivered throughout the 2014/2015 financial year.
1. Current Projects
Over the past 3 months there has been significant progress and escalation in activities around
the delivery of capital projects. There are currently 159 active projects in the 2014/15 capital
program with a value of $24.2m as of 19 March 2015. There are 31 projects completed and the
remaining projects within the program have commenced and are in varying stages of delivery.
Some of the projects that have been completed recently include:
• Noosa Waters Revetment wall scour protection
• Noosaville Landfill Sediment Basin
• Noosa Heads Sunshine Beach Rd (Noosa Junction) Disabled Parking Bay
• Tewantin Martin Park Skate Park
• Sunshine Beach Beach Access 35
• Boreen Point Old Tennis court site rehabilitation
• Tewantin Cooroy Noosa Rd & Beckmans Rd Intersection improvements
• Sunrise Beach Ben Lexcen Drive Safety improvements design
• Peregian Beach Rufous Street site demolition
• Botanical Gardens Park furniture renewals
Page 21 of 29