Purpose:
Provide a standard procedure for the installation of check dams to control flow velocity
in drainage channels such as table drains, swales etc.
Check dams are not to be used in "defined" watercourses
Materials Required
n Rock
• Geofabric bags approximately half full of 50-70mm stone or gravel
or
n Sandbags
Procedure: Sediment Flow
Build up
Installation
Locate check dam in straight section of
drain
Limit height of check dam to around 0.5m
Centre of check dam should be a Spill way
minimum of 150mm lower than the outer
edge to form a spillway
Spacing of rock check dams should be
such that the base of each check dam is Cross Section
no higher than the top of the check dam
below it, Figure 1. Rock Check Dam in Table Drain
Maintenance
Although the primary purpose is to
control flow velocity, check dams will trap
sediment on the upslope side. This
sediment should be removed before it
accumulates to half the original height of
the check dam.
Check Dams Document Number Page 1 of 1
Issue Number 1 July 2008 QMS 073 Authorised by: C. Gursanscky
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Amended Plans for approval - Bunnings WarehouseRelated documentApplication case desk ↗
About this file
- File size
- 57.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.