CLEARING

The proposed development retains all the significant trees on the property.
Identified on the Tree Protection Plan Rev A 11/08/2017 prepared by Myles
Baldwin Design and in accordance with AS 4970—2009. Protection Of Trees
On Development Sites.

A number of smaller trees previously planted by the owner of No. 12 Park
Road will be removed to allow access and for construction of footings.
(Refer to Survey/Engineering Plans). On completion a similar tree will be
replanted in each original location on site and in the road reserve to provide
and effective visual barrier to the undercroft of the proposed deck

Prior to construction all trees will be clearly tagged and recorded on a survey
plan. On completion the trees will be resurveyed to ensure full compliance
with the conditions of the Development Approval.

All work on the subject site is to be undertaken in accordance with the approved
Tree Protection Plan, Development Permit for Operational works
(Landscaping), Construction Management Plan and conditions of Council
Approval.

No regarding of the slopes within the Tree Protection Zone will be permitted.
The regrading of the slopes (to improve overall long term stability) beneath
the terrace will disturb the existing vegetation. On completion it is proposed
to replant beneath the terrace with shade tolerant native species.

ACCESS AND PARKING

The access for construction materials and equipment will be from Park Road
via the existing driveway to No. 10 Park Road. The Builder is to submit
written consent for the use of this access driveway and garage from the
owner of No. 10 Park Road. Access for personnel will be via’ Allambi Rise
and Park Road. Offsite parking will be required for most construction
personnel.

Most workers vehicles shall be parked in Allambi Rise or in the existing
driveway and carport of 12 Park Road which is accessed by the 9A driveway
Allambie Rise.

All construction access is to be obtained from Allambi Rise via the existing
easement subject to the following exceptions:

a) A crane may be used for delivering prefabricated materials and the pier
digging machine to the site.

The use of the crane in Park Road is to occur on two (2) separate days only,

first for the delivery of the pier digging machine and any prefabricated

materials, the second to retrieve the pier digging machine and provide any

further prefabricated materials as required.

Traffic control is to be provided for the use of the crane in Park Road, in

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.