accordance with the builders Traffic Management Plan.

b) Access from Park Road to the site is to be used for the purpose of a
concrete pumping pipe to be located at the base of the rock retaining wall
on the boundary of 10 Park Road, laid upon a composted wood chip mulch
600mm wide and 150mm thick. Any mulch contaminated by concrete or
wastes shall be removed from the site. Any remaining clean mulch may be
left in situ and spread to 50mm thickness.

MATERIALS HANDLING

As previously described all prefabricated building materials will be delivered to
site via Park Road. Manual! material handling will be employed throughout the
construction to minimize construction activities and impact on the site,
especially existing vegetation.

In addition a temporary builder's hoist a temporary scaffold platforms will be
erected in the existing driveway and within the property boundaries of 10
and 12 park road including a builders hoist over the existing Driveway to
accommodate the mini concrete pump waste grout receptacles and to
facilitate the easy removal of waste without using or traversing the road
reserve.

Temporary scaffold platforms and walkways will be constructed within the
property boundaries in accordance with the Tree Protection Plan & AS 4970 to
minimize foot traffic on the slope and compaction of soils when relocating
equipment.

Building waste will be collected and removed daily in a garbage trailer or light
truck located adjacent to the garage of No.10 Park Road. In order to minimize
waste and hence its removal, most building materials will be pre- engineered
and delivered to site pre-cut to the appropriate size.

Deliveries will be by light truck (6T) in small loads which will be
manhandled to site

At this stage it is envisaged that the following elements will be
pre- engineered prior to delivery:

Micro piles

Reinforcing steel for footings
Structural steel posts and bearers
Timber joists and flooring
Scaffolding support

e@ e@ @ © @

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.