CONSTRUCTION PROGRAMME

The proposed Construction Program is summarized below:

 

Operation

Month 1

Month 2

Month 3

Month 4

Month 5

Month 6

 

Site Establishment

#

 

New Access Path

#

 

Construct Working Platform

 

Install Micro Piles

 

Construct Pipe Caps

 

Erect Scaffolding

 

Construct steel columns and
bearers together with timber
Joists and decking to terrace.

 

Install Stormwater Reticulation

 

 

Install Landscaping

 

 

 

 

 

tk

 

 

ENVIRONMENT MANAGEMENT PLAN

The method of construction does require the use of a crane. This offers
significant environmental advantages as summarized below:

e By utilizing micro piling to ensure the stability of footings no tracked

 

machine will be required to access the site. The piling rig can be man

handled around the site after being craned into position utilizing

protective temporary walkways and level platforms installed in

accordance with AS 4970—2009

Manual material handling will be employed throughout the construction

to minimize construction activities and impact on the site, especially

existing vegetation.

All construction and materials handling will be undertaken beneath the

tree canopy thereby avoiding potential damage to the canopy

All significant and protected trees within the work area will be fenced
and or otherwise protected during construction in accordance with the
Tree Protection Plan Rev A 11/08/2017 prepared by Myles Baldwin
Design and in accordance with AS 4970—2009

The Builder is to utilize where possible all trades and workers who

were involved in building the residence on No. 12 Park Road. This will

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.