ensure that all workers understand the sensitivity of the site, the
importance of preserving the vegetation and the need to minimize
noise, dust and other building activity impacts on adjacent home
owners and the public.

e The working area will be minimized to protect any significant
vegetation

REMOVAL OF BUILDING WASTE

Building waste will be collected in a garbage trailer or light truck situated
adjacent to the garage of No. 10 Park Road. Sand spoil will be lowered daily
from the terrace platform to the garbage trailer or light truck located adjacent
to the garage of No.10 Park Road.

EROSION AND SEDIMENT CONTROL

Erosion and Sediment Control is considered for both work areas as
summarised below:

e The driveway to park Road will require silt fences to be installed to the
perimeter of the works. Sand bags will be placed in the gutters during
excavation and concreting to prevent runoff into the Council storm
water system.

e Erosion and Sediment Control for the proposed terrace will require a
silt fence to the perimeter of the proposed footing excavation.

e The permanent storm water drainage system will be connected to the
Council system as an early works operation to prevent any
concentrations of runoff discharging onto the sand slope.

Environmenial Controls Plan to prevent pollution from concreting operations
during the construction (Grouting & Pile Caps)

Background.

The use of concrete materials is reduced to a minimum due to the use of a micro
piling system which is to be craned onto site.

The small volumes of concrete required allow the use of a small concrete grout
pump with reduced line size to grout piles and concrete pile caps.

This system gives precise control to the operators making spillage and cleaning
requirements negligible.

Controls:

The builder/site manager will ensure the following best practice sediment control
measures including a designated wash down area are in place before work starts
and are adequately maintained throughout construction.

e The designated wash down area is to be located within the site on the
existing paved driveway with sediment control screening in place and an
appropriate HDP waste receptacle drum will be available to retain any
sediment waste from swept up spillage or cleaning of equipment.

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.