The drum will be secured onto the main frame of the vehicle ready for
transportation.

The drum will be secured with a bracket that is easily accessible to the
operator.

The drum will be removed from the bracket and the waste water emptied

into the designated treatment facility once the truck returns to the yard with
ihe the wastewater containing suspended solids being recycled back into the
plant.

e The vehicle will be washed down at the depot.

e Delivery vehicles will be on paved surfaces at all times and so no mud soil
and or stones will be carried off site as pollutants.

e Inspect roads for any sediment that has been tracked off site and sweep it
back on site.
(This will be done if there is threat of rain and at the end of each day). A
hose will not be used to wash it away.

INSTALLATION OF PILES AND CAPPING

Methodology for installation of hollow bar micropiles as deep foundation support for
the new timber deck.

The micropiles consist of one or more outers steel casings installed to the
depths indicated on the piling subcontractor (PCA) drawings. A central steel
reinforcing element consisting of a 40/20 hollow bar is to extend to a pre-
determined design depth below the casing to form the bond length and develop
the applied load.

After checking the the project drawings for the details of the micropile
arrangement for each pile location (designed in accordance with the Tree
protection plan.) the Tree protection plan, the construction management plan
and relevant environmental protection documentation and instructions the rig
will be craned into position for the first pile onto a previously established level
temporary protective platform constructed in accordance with the tree
protection plan and AS4970 - 2009.

Drilling will be carried out using a 90mm EXxX drill bit using a rotary top hammer
for installation and all installation specifications accurately recorded for this and
all subsequent piles.

The piles are grouted as the work proceeds and any excess grout is collected
and pumped into storage containment for offsite disposal in accordance with
the concreting operations environmental protection plan.

The process is repeated for subsequent piles.

The onsite grouting pump will be contained within its own bunded area which
will be kept clean as the work proceeds and managed in accordance with the
above Environmental Controls Plan to prevent pollution from concreting
operations during the construction.

Pile capping is to be managed in the same way as the grouting procedures.

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.