PCA-WI-001
p C A Work Instruction - Micropiling

MUM GROUND ENGINEERING Uiglaaly Revision No: 4 Issue Date: 5/02/16

 

 

 

 

All Printed Copies are Uncontrolled Page 4 of 7

 

Type and length of steel elements used including;
o Overall length of hollow bar
© Length of hollow bar above the casing
o Length of hollow bar below the top of the casing
Grout quantity
Pile number
Drawing number
Project number
General comments

Changes to the installation records may be required from time to time upon

approval of the Engineering Manager.

4.1.4

Site preparation for casing and micropile installation

Check the relevant project drawings for the details the micropile
arrangement for each pile location.

Assess environmental and safety requirements for carrying out the works to
ensure the micropiles can be installed within the project requirements.

Install gantry system and ensuring the gantry legs will not interfere with the
production piling activities.

Install scaffold to enable workers to set the drill and materials in position.
Establish a bunded area for the operation of the grout plant.

4.1.5 Drilling and Installation of Micropiles

This section of the work instruction sets out the procedures to be used to ensure the

successful installation of the micropiles.

Vi.

Setup the drill in position such that the steel casing can be guided into
position.

Assess grout management procedures to ensure excess grout can be
collected and pumped into storage containment for offsite disposal.

Assess environmental controls for noise and dust are suitable and meet the
requirements of the project.

Check the finished height required for the casing

Check that the casing is at the correct angle.

Drill the casing to the required depth.

 

Used in these records

About this file

File size
26.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Application OPW17-0561.pdf · 26.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.