OPW052025 Report - Part 2

Attached to the e-mail Operational Works Application OPW25/0093 - OPW Report Part 2 _May 2025 - 146 Middle Creek Road_ Federal - Email 2 of 2.

of 107

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (17.0 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Tables
Table 1: Summary of CBR Laboratory Results .................................................................................................................... 10
Table 2: Stability Risk Levels ...................................................................................................................................................... 14
Table 3: Details of Qualitative Risk Assessment for Property (AGS 2007) ............................................................... 15
Table 4: Retaining Wall Design Parameters.......................................................................................................................... 23

Text Figures
Text Figure 1: Sketch of proposed works (provided by SQ)............................................................................................. 2
Text Figure 2: May 2024 aerial image of lot and surrounds (courtesy Queensland Globe)................................. 3
Text Figure 3: Topography of site and surrounds, hillshade applied (courtesy Qld Globe) ................................ 4
Text Figure 4: Veiw from lowest intermediate knob (LHS) & along driveway alingment above
      existing sheds (RHS) ............................................................................................................................................................ 5
Text Figure 5: Looking south-west from saddle (LHS) & north-east at sidelong cut (RHS) ................................ 6
Text Figure 6: View of final rise to house site, looking west ............................................................................................ 6
Text Figure 7: Looking north over proposed house site ................................................................................................... 7
Text Figure 8: Extract of Gympie Surface Geology Map .................................................................................................... 8
Text Figure 9: View of weathered phyllite in cutting adjacent to sidelong section of track ................................ 8
Text Figure 10: Finished excavation - test pit TP3 ............................................................................................................... 9
Text Figure 11: Extract of NC Landslide Hazard Overlay Mapping.............................................................................. 13
Text Figure 12: Extract from Slope/W Analysis (Section A-A'- including adverse groundwater
      condition) .............................................................................................................................................................................. 16
Text Figure 13: Extract from Slope/W Analysis (Section B-B'- including adverse groundwater
      condition) .............................................................................................................................................................................. 17
Text Figure 14: Concept drainage arrangements ............................................................................................................... 18
Text Figure 15: Footing depth required to minimise the risk of undermining and surcharge loading ......... 22

Appendices
Appendix A                      Test Pit Logs & Explanatory Notes
Appendix B                      Laboratory Test Certificates
Appendix C                      AGS 2007 Practice Note Guidelines for Landslide Risk Management & Qualitative
                                Terminology for Use in Assessing Risk to Property
Appendix D                      Limitations

Figures
Figure 1: Site Plan




Geotechnical Investigation & Slope Stability Assessment
9 April 2025 | 25050-001-Rev0                                                                                                                                                                 iv
Log in to download the original file

OPW052025 Report - Part 2.pdf · 17.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗