RFI - Attachment B - Stormwater management Report · MCU20/0026

of 54

Text shows just the words. Original shows the document exactly as it was published.

Original PDF page 12, section 1. The text section number identifies this passage in the reader.

           Issue            Desired Outcomes



                            4. Provide emergency spillways for sediment basins to achieve the
                               construction phase stormwater management design objectives for
                               emergency spillways on temporary sediment basins (part 3).

 Erosion Control            1. Stage clearing and construction works to minimise the area of exposed
                               soil at any one time.

                            2. Effectively cover or stabilise exposed soils prior to predicted rainfall.
                            3. Prior to completion of works for the development, and prior to removal
                               of sediment controls, all site surfaces must be effectively stabilised
                               using methods which will achieve effective short-term stabilisation.

 Sediment Control           1. Direct runoff from exposed site soils to sediment controls that are
                               appropriate to the extent of disturbance and level of erosion risk.

                            2. All exposed areas greater than 2500 metres must be provided with
                               sediment controls which are designed, implemented and maintained
                               to a standard which would achieve at least 80% of the average annual
                               runoff volume of the contributing catchment treated (i.e. 80%
                               hydrological effectiveness) to 50mg/L Total Suspended Solids (TSS) or
                               less, and pH in the range (6.5–8.5).

 Litter, Hydrocarbons and   1. Remove gross pollutants and litter.
 other contaminants
                            2. Avoid the release of oil or visible sheen to released waters.
                            3. Dispose of waste containing contaminants at authorised facilities.

 Waterway Stability and     1. Where measures are required to meet post-construction waterway
 flood flow management         stability objectives, these are either installed prior to land disturbance
                               and are integrated with erosion and sediment controls, or equivalent
                               alternative measures are implemented during construction.

                            2. Earthworks and the implementation of erosion and sediment controls
                               are undertaken in ways which ensure flooding characteristics
                               (including stormwater quantity characteristics) external to the
                               development site are not worsened during construction for all events up
                               to and including the 1 in 100 year ARI (1% AEP).




11 June 2020                          Stormwater Management Report                                         9
S20-023                             40 Park Crescent, Sunrise Beach

Used in these records

About this file

File size
7.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

RFI - Attachment B - Stormwater management Report.pdf · 7.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.