10 Appendix 1 – Environmental Site Procedures
10.1 Site establishment
Objective
• Compliance with obligations under the Act and any Development Approval conditions
• Minimisation of potential environmental risks from activities
Management Strategy
• Communication with surrounding neighbours about works on site via a letterbox drop
• Site management controls are set up in accordance with the stormwater and erosion
plan (refer to Appendix 2)
• Ensure the EMP Aspects Register is completed
• All staff working on site are to undertake a site-specific induction to be delivered by the
Site Foremen/Manager or McNab representative
• Site facilities and stockpiles are to be established and stabilised as early as practicable to
prevent undue disturbance to vegetation and soils as works progress
• Site facilities are to be located in a flat area at least 20m from drainage paths and the
waterway
• Controls and protection measures such as bund or geo-fabric covers should be
established prior to works commencing where possible
Action / Corrective Action
• Implement Management Strategies as above
• Corrective measures are to be agreed to in conjunction with the HSE team
Performance Indicators
• Evidence of Site Induction by personnel
• Site Facilities and stockpiles placed in accordance with the above management strategy
10.2 Community consultation
Objective
Adjoining stakeholders should understand the extent of works and the impact that works may have
on them.
Management Strategy
Stakeholders must be aware of the potential impacts and duration of works, in addition to the
process for making complaints.
Any concerns/ complaints raised by the community should be addressed in accordance with the
complaints procedure.
Action / Corrective Action
Send correspondence to adjoining stakeholders notifying of works.
Ensure that information is available at the access points in the form of a builder’s sign, including
phone numbers of designated personnel.
Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan Page 24 of 39
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.