Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                   mcnab construction
                                                                                    07-DOC-003 Rev 4

10.14           Water supply
Objective
   •      To ensure Water Supply for site is compliant
   •      To conserve natural resources

Management Strategy
  •     Water for site will be obtained from the metered point close to site
  •     Water supply for the civil works will come from means other than mains supply, for
        example recycled water, or a bore or dam, and will be transported in a water carrier
        indicating non-potable water
  •     Awareness and education via Inductions and toolbox training on waste management,
        energy and water saving practices in construction plant and equipment
  •     Awareness and compliance with Project Specific Environment Conditions
  •     Substitute water rich techniques (e.g. hosing for dust control or cleaning) with
        alternative techniques, such as:
         Minimise plant movements
         Restricting movements in high wind
         Application of dust sealant material
         Using a brush instead of water for cleaning
         Check for any water leaks and use water sparingly

Action / Corrective Action
   •      Site Foreman to monitor compliance for water supply

Performance Indicators
   •     No non-conformances resulting from internal audits
   •     No infringements or notices issued from authorities

10.15           Restriction to vehicle access
Objective
   •      To restrict vehicle access to the project site to those directly involved in construction on
          site

Management Strategy
  •     Erect temporary 1800mm high chain wire fence or fully sheeted hoarding
  •     Temporary fencing/hoarding to remain intact for the duration of the project
  •     Display signage on temporary fencing/hoarding informing personnel and others that
        pedestrian or vehicular access is not permitted – DANGER CONSTRUCTION SITE NO
        UNAUTHORISED ENTRY
  •     Communicate requirement to all site visitors and workers during site induction
  •     Permanent fencing to be installed in accordance with specification

Action / Corrective Action
   •      Project Manager shall ensure that the above management strategies are followed
   •      Site Foreman will monitor compliance with restriction




Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan                                                                                     Page 32 of 39

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.