Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                 mcnab construction
                                                                                  07-DOC-003 Rev 4



Management Strategy
  •     All works on site shall be managed in accordance with the relevant Acts and Regulations
  •     All site personnel will be made aware of the soil contamination indicators, which may
        include but are not limited to:
                  Disturbed, discoloured or stained soil
                  Bare soil patches
                  Odorous liquids
                  Disturbed or distressed vegetation
                  Unpleasant odours
                  Poor quality of surface water
                  Presence of fill
  •     Upon identification of any of the above indicators, work must cease immediately and it
        must be reported to the Site Foreman
  •     The Site Foreman must report the discovery in accordance with procedures outlined in
        Appendix 11.7 Reporting Environmental Incident or Complaint
  •     Where possible, all existing fill material excavated from within this portion of the work is
        used to backfill the pipeline trench in preference to naturally deposited alluvial soil
  •     Soil that requires disposal off-site will require assessment to determine if a disposal
        permit from the EPA is required and further advice must be sought
  •     In the event the soil is classified as ‘clean’, the material can be re-used onsite or
        transported offsite for appropriate re-use
  •     If soil is classified as contaminated, a Disposal Permit will be required from the EPA. The
        soil will be required to be transported offsite to an appropriately licensed waste
        handling facility

Action / Corrective Action
   •      The Project Manager shall ensure that the above management strategies are followed
   •      The Site Foreman will ensure all site personnel are informed of this site procedure,
          monitor all excavation work and look for any contaminated soil indicators in the
          immediate work areas

Performance Indicators
   •     Identification of suspected contaminated soil indicators are immediately reported and
         the work is ceased until it has been clarified by the relevant authority

10.18          Working within a water corridor
Objective
   •      To implement measures so as to comply with Water Act 2000 and Water Regulation
          2016




Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan                                                                                   Page 34 of 39

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.