Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239
Plans and drawings: the text below has words only, no drawings.
mcnab construction
07-DOC-003 Rev 4
Management Strategy
• Signage is to be erected indicating that the works are being carried out under
appropriate guidelines
• Where possible, activities are to be timed to coincide with periods of no or little flow
• Activities are to be completed as quickly as possible
• The area of disturbance must be no greater than the minimum area necessary for
upgrading the sewer
• The extent and duration of bare surface exposure must be minimised and protected
from weathering, raindrop impact and water run-off
• Clean water run-off must be diverted around areas of disturbance where practicable
• Sediment must be captured and retained on site
• Bed and bank stability must be managed to minimise erosion and reduce sedimentation
• Machinery to be used should be selected on the basis of type and size necessary to
achieve minimal disturbance of the site. In addition, machinery is to be stored, refuelled
and maintained outside the high banks of the creek
• Excavation must be undertaken in a way that does not interfere with the flow of water
to the downstream environment and downstream users
• Material excavated that is not waste material must be spread evenly within the bed and
banks of the waterway and must not interfere with the flow of the waterway
• Constructed drainage and discharge structures must not alter the natural bed and bank
profile
• Upon completion, revegetation of disturbed areas is to occur with native vegetation
endemic to the area and/or installation of erosion protection measures where
appropriate
Action / Corrective Action
• The Project Manager shall ensure that the above management strategies are followed
• The Site Foreman shall monitor compliance with work activities site
Performance Indicators
• Reports from site audits conducted by the HSE team indicates no corrective action
requirements
• The HSE team will be immediately informed of any breach of this site specific
requirement
10.19 Fire Ants
Objective
• The identification and notification of Red Imported Fire Ants (RIFA) to prevent the
spread of the Fire Ants in Queensland
• Prevention of the importation of RIFA into the construction zone
Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan Page 35 of 39
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.