mcnab construction
07-DOC-003 Rev 4
Management Strategy
• Where suppliers are operating from a restricted area, only use those that have a DAF
Approved Risk Management Plan (ARMP)
• In addition to the start-up inspection, the Project Manager will engage a DAF approved
Fire Ant Inspector to check work site and a surrounding 10 metre radius (buffer zone) for
the presence of RIFA and every 28 days during the project
• All incoming Fire Ant Carriers (i.e. Soil, hay, potted plants, quarry material) must be
visually inspected prior to unloading or as soon as practicable
• All incoming restricted plant found to contain fire ants must be reported immediately to
Biosecurity Queensland
• Keep records (for a 12 month period) of all incoming restricted plant. Records should
detail the nature, quantity and source of materials imported to the site. Records shall be
kept on site
• Random audits comprising visual inspections by the Site Foreman or other trained
personnel should be undertaken for incoming restricted plant
• Plant is not to be accepted onto a work site unless free of all soil deposits
• Any restricted plant that may be moved off-site at a later date are to be stored as per
McNab’s DAF Approved Fire Ant Management Plan
• All restricted material must remain within the restricted area or be disposed of at a
Biosecurity Queensland approved landfill
• Fire Ant sightings must be reported to Biosecurity Queensland on 13 25 23 within 24
hours
• Fence off suspected nests and seek advice from the Biosecurity Queensland before
proceeding with works
• If the project site is located within a Fire Ant Restricted zone. The work site should be
managed in accordance with McNab’s DAF Approved Fire Ant Management Plan
Action / Corrective Action
• Follow McNab’s DAF Approved Fire Ant Management Plan
• Contact the Biosecurity Queensland for additional advice and direction
Performance Indicators
• No importation or spread of fire ants from McNab’s site
• No personnel injured due to fire ant bite
10.20 Weed Management
Objective
• Prevention of the importation of declared plants or noxious weeds into the construction
and operational zones
• To comply with the statutory EA conditions and Project EIS
• No spread of weeds to any other location as a result of vehicle movements and
construction activities
• Wash-down facilities to comply with DEHP design guidelines
Infinity Apartments – Gympie Tce Noosaville Environmental Management
Plan Page 36 of 39
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.