Construction Management Plan


  3.4           Structure

               3.4.1   Footings / Foundations
               Construction of the footings and foundations will be undertaken using conventional methods.
               Generally, all footings and foundations will be high level structures.
               Piling of any type is not anticipated.

               3.4.2   Structural Walls
               The bulk of the structural walls are a combination reinforced concrete block walls and structural
               framing with light weight cladding.
               Retaining walls will be constructed conventionally and will be reinforced concrete blockwork
               structures.

               3.4.3   Roof
               The roof will be a traditional structural timber framed roof (Trusses) with metal deck roofing and
               proprietary insulation below.


  3.5           Façade

  The external walls (Façade) are predominantly structural timber framing with compressed fibre cement
  cladding with paint finish.

  All external windows will be commercial grade windows with appropriate treatment for energy efficiency as
  required as well as any acoustic properties prescribed in the Approvals.


  3.6           Services & Finishes

  Services and finishes activities will commence once roof framing has been installed. Internal walls will
  initially be set out, and the top and bottom tracks installed to allow final coordination of services and to
  ensure passive fire systems are installed in the correct location. Rough in services works will consist of
  high- level mounted ductwork and pipework which are not reliant on the envelope being water-tight. Once
  the windows and cladding have been installed to the façade, the finishes and services fit off will
  commence.


  4.0           Site Setup and Materials Handling

  The site will be contained and secured with a commercial site fence with appropriate bracing and shade
  clothe to minimize noise, dust and provide security. All construction works relating to the construction of
  the dwellings will take place within the construction zone defined y the site perimeter fencing.



  4.1           Traffic Management

  QldBUILT have engaged a certified traffic management organisation to develop a detailed, site specific
  Traffic Management Plan / Traffic Guidance Scheme.




Document:                CMP01      Construction Management Plan        [Version 2.0]       Scheduled Review Date:   30/10/2024

Page 9 of 18             qldBUILT Pty Ltd | Uncontrolled when printed                              Date Reviewed:    Xx/xx/xx

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.