Construction Management Plan
3.3 Demolition Works
Major demolition within the site will be undertaken by others before qldBUILT establishes site.
Only very minor demolition scope, remaining grubbing etc. will form art of this scope of this CMP.
3.3.1 Site Clearing
Tree clearing will be done by other before qldBUILT establishes site and will not form part of the scope
of this CMP.
The site will need to be stripped of topsoil, which, if possible, will be stockpiled on site for use later. The
Site earthworks and drainage will be completed strictly in accordance with any Operational
requirements, guidance or restrictions.
3.3.2 Bulk and Detailed Excavation
Following a detailed assessment of the current preliminary structural design and civil documents, the
bulk excavation of the site will be traditional in the overall approach.
High level footings will be installed to support the building structure any material removed from
footings will be utilized on site where possible or removed from site.
Detailed excavation works will be concentrated on the high-level pad and strip footings and will
commence once bulk excavation has been completed.
There should be no requirement for any Dewatering, there may be some localized dewatering to
remove water from any footing excavations or the like.
Any localized dewatering planned will be developed as part of a site Construction Environmental
Management Plan (CEMP)
Prior to any excavation work, QldBUILT Construction will finalise an approved Construction
Environmental Management Plan, which is currently available in draft form.
Please Refer to Appendix 2 – Draft Construction Environmental Management Plan
(CEMP)
Environmental controls that may be implemented include a shaker grate, all weather access,
sediment fences and socks, and temporary detention basins for stormwater.
A preliminary Erosion and Sediment Management Plan in accordance with the International
Erosion Control Association (IECA) guidelines for the site has been developed.
Please Refer to Appendix 3 – Draft Erosion & Sediment Control Plan (ESCP)
The excavation and retention sequence will likely follow is as follows: -
Site establishment and detention devices
Strip Topsoil / Bulk excavation and haul roads
Benching for Building Pad and Carparks
Footings
Retaining walls construction
Backfill retaining walls.
Inground Services and Footings
Document: CMP01 Construction Management Plan [Version 2.0] Scheduled Review Date: 30/10/2024
Page 8 of 18 qldBUILT Pty Ltd | Uncontrolled when printed Date Reviewed: Xx/xx/xx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.