Construction Management Plan
4.7         Waste Management

Rubbish bins / skips will be provided at strategic positions around the site, where all subcontractors will be
required to clear their rubbish as it accumulates. These bins will be located around the building and loaded
via forklift into the large skips for removal from site. Change overs will occur as bins are full.


                4.7.1   Recycling
Mixed waste bins will be provided with recycling occurring offsite. There is scope for recycling of
reinforcement steel, formwork and concrete at various stages of the project. During fit out, a plaster bin will
be provided by subcontractors to remove plasterboard waste. Subcontractors are to provide their own
smaller bins (or 120/240L wheelie bins) to transport waste to qldBUILT’s bins.
Food waste bins will be placed at each lunchroom, as well as a central 2m3 bin. The food waste bin will be
located at both amenities areas with lids to hold food waste.



4.8         Temporary Infrastructure

qldBUILT has ascertained that there is sufficient water and power available to service the requirements
of the site during construction.

                4.8.1   Temporary Hydraulics
                Temporary hydraulics including cold water, hot water, sewer and drainage will be provided where
                required to:
                     Site toilets, hot water boilers
                     First aid and lunch amenities
                     Site office amenities and kitchens
                     Bubblers
                     Wash-outs as required

                A separate temporary plumbing application will be made to Council in due course.

                4.8.2   Construction Power
                Temporary electrical services including power, lighting, and data will be provided where required to:
                    Temporary lighting to work zones and emergency egress exit lighting
                    Temporary power boards on site
                    Power for site amenities

                4.8.3   Fire Control Measures
                Temporary fire control measures consist of:
                    Hot work permits will be used onsite
                    Good housekeeping will ensure fire risks are reduced
                    Fire drills included as part of emergency procedures
                    Emergency Management Plan
                    Management of Hazardous chemicals
                    Fire extinguishers on site




Document:                CMP01      Construction Management Plan        [Version 2.0]       Scheduled Review Date:   30/10/2024

Page 11 of 18            qldBUILT Pty Ltd | Uncontrolled when printed                              Date Reviewed:    Xx/xx/xx

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.