Construction Management Plan
4.7 Waste Management
Rubbish bins / skips will be provided at strategic positions around the site, where all subcontractors will be
required to clear their rubbish as it accumulates. These bins will be located around the building and loaded
via forklift into the large skips for removal from site. Change overs will occur as bins are full.
4.7.1 Recycling
Mixed waste bins will be provided with recycling occurring offsite. There is scope for recycling of
reinforcement steel, formwork and concrete at various stages of the project. During fit out, a plaster bin will
be provided by subcontractors to remove plasterboard waste. Subcontractors are to provide their own
smaller bins (or 120/240L wheelie bins) to transport waste to qldBUILT’s bins.
Food waste bins will be placed at each lunchroom, as well as a central 2m3 bin. The food waste bin will be
located at both amenities areas with lids to hold food waste.
4.8 Temporary Infrastructure
qldBUILT has ascertained that there is sufficient water and power available to service the requirements
of the site during construction.
4.8.1 Temporary Hydraulics
Temporary hydraulics including cold water, hot water, sewer and drainage will be provided where
required to:
Site toilets, hot water boilers
First aid and lunch amenities
Site office amenities and kitchens
Bubblers
Wash-outs as required
A separate temporary plumbing application will be made to Council in due course.
4.8.2 Construction Power
Temporary electrical services including power, lighting, and data will be provided where required to:
Temporary lighting to work zones and emergency egress exit lighting
Temporary power boards on site
Power for site amenities
4.8.3 Fire Control Measures
Temporary fire control measures consist of:
Hot work permits will be used onsite
Good housekeeping will ensure fire risks are reduced
Fire drills included as part of emergency procedures
Emergency Management Plan
Management of Hazardous chemicals
Fire extinguishers on site
Document: CMP01 Construction Management Plan [Version 2.0] Scheduled Review Date: 30/10/2024
Page 11 of 18 qldBUILT Pty Ltd | Uncontrolled when printed Date Reviewed: Xx/xx/xx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.