qldBUILT Construction Management Plan - JURA Rev02 · MCU23/0094

of 81

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (17.3 MB): may take a few minutes to open.

Log in to see the plans as drawn
 FPE Ref: 6693-240215-1.0



          6.3      FAUNA MANAGEMENT

          Objective         To minimise direct impacts on wildlife during clearing and construction, particularly conservation significant species.

          Potential         ▪   Disturbance of arboreal and nesting habitats leading to death or injury of fauna.
          Impacts           ▪   Potential impacts to ground-dwelling fauna such as reptiles.

          Performance       ▪   No fauna killed, injured, or orphaned as a result of site works.
          Criteria          ▪   No Koalas impacted.




                                                                                                   T
          Definitions       ▪   FSC (Koala qualified) means a person who has demonstrated experience in locating Koalas in Koala habitats and has appropriate




                                                                                      AF
                                permits/licences from DES to capture and relocated native fauna.

          Control           ▪   Clearing works have been be completed. Any additional clearing must only be done under a Species Management Program Low Risk of Impact




                                                                                R
          Measures              approved by DES.

          Monitoring        The following inspections will be carried out:
                            ▪
                                                                             D
                                Works are to proceed following completion of pre-clearance surveys.
                            ▪   No disturbance is occurring outside designated construction zone.
                            ▪   Regular site checks to ensure no incidents have occurred involving fauna, including entrapment.

          Reporting         ▪   Contractor to maintain a log of inspections, maintenance action and inductions.
                            ▪   The log is to be kept for verification of compliance on an as need basis.
                            ▪   Any wildlife caught and relocated, or injured/killed on site, are to be logged and reported to DES within 30 days.




15 February 2024                                            Construction Environmental Management Plan                                                                   14
                                                  79 - 83 Eumundi Noosa Road & 26 Headland Drive, Noosaville QLD

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.