Construction Management Plan
  2.2           Site Constraints

  The site has very few site constraints from the point of view of surrounding road networks and
  neighbouring properties. Generally, all construction activities can take place within a fenced
  construction zone.

               There are public road site access points to the front and side of the site which will be
                maintained during the building process. Consultation and coordination with surrounding
                stakeholders will be required.
               Power, water and sewer supply upgrades will be a requirement for the project and may
                involve some works by the supply authorities outside the boundaries of the site and
                additional works within the site. Separate specific work plans will be developed for this
                works once the design and scope has been finalised.
               There are existing residential buildings on the Southern and Eastern Boundaries which will be
                separated from the construction zone by existing or additional temporary fencing. .
               There is a vacant lot to the Northern Boundary.

  2.3           Site Considerations

  Careful site management, which will minimize disruption and inconvenience to neighbouring buildings
  and their occupants, is of the highest importance. qldBUILT will provide 2 points of contact to work with
  neighbours to understand their needs and requirements, and, where possible, adjust construction works
  methodologies accordingly.

  Also refer to Section 5.0 – Adjoining Owners Management.

  2.4           Proposed Development

  The proposed redevelopment comprises a 2-storey building including:

      •        12 x 2-bedroom 2 storey small dwellings
      •        24 x 2-bedroom single storey small dwellings
      •        2 x 3-bedroom split level 2 storey units
      •        Covered car space and storage for each 2-bedroom dwelling and 2 covered spaces for the 2 & 3-
               bedroom dwellings.
      •        10 visitor car spaces
      •        Common area swimming pool
      •        Demolition of existing dwellings on the site (by others)


  2.5           Key Items

  Whilst preparing this CMP qldBUILT has identified the following key items and attributes:
              Management of the Bulk Earthworks
              Silt & Sediment Control generally
              Safe Vehicle Access and Egress to and from the site during construction
              Due consideration of neighbouring properties and local residents at all times during
               construction.




Document:               CMP01      Construction Management Plan        [Version 2.0]         Scheduled Review Date:   30/10/2024

Page 6 of 18            qldBUILT Pty Ltd | Uncontrolled when printed                                Date Reviewed:    Xx/xx/xx

Used in these records

About this file

File size
17.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

qldBUILT Construction Management Plan - JURA Rev02.pdf · 17.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.