qldBUILT Construction Management Plan - JURA Rev02 · MCU23/0094
Plans and drawings: the text below has words only, no drawings.
Very large file (17.3 MB): may take a few minutes to open.
Construction Management Plan
2.2 Site Constraints
The site has very few site constraints from the point of view of surrounding road networks and
neighbouring properties. Generally, all construction activities can take place within a fenced
construction zone.
There are public road site access points to the front and side of the site which will be
maintained during the building process. Consultation and coordination with surrounding
stakeholders will be required.
Power, water and sewer supply upgrades will be a requirement for the project and may
involve some works by the supply authorities outside the boundaries of the site and
additional works within the site. Separate specific work plans will be developed for this
works once the design and scope has been finalised.
There are existing residential buildings on the Southern and Eastern Boundaries which will be
separated from the construction zone by existing or additional temporary fencing. .
There is a vacant lot to the Northern Boundary.
2.3 Site Considerations
Careful site management, which will minimize disruption and inconvenience to neighbouring buildings
and their occupants, is of the highest importance. qldBUILT will provide 2 points of contact to work with
neighbours to understand their needs and requirements, and, where possible, adjust construction works
methodologies accordingly.
Also refer to Section 5.0 – Adjoining Owners Management.
2.4 Proposed Development
The proposed redevelopment comprises a 2-storey building including:
• 12 x 2-bedroom 2 storey small dwellings
• 24 x 2-bedroom single storey small dwellings
• 2 x 3-bedroom split level 2 storey units
• Covered car space and storage for each 2-bedroom dwelling and 2 covered spaces for the 2 & 3-
bedroom dwellings.
• 10 visitor car spaces
• Common area swimming pool
• Demolition of existing dwellings on the site (by others)
2.5 Key Items
Whilst preparing this CMP qldBUILT has identified the following key items and attributes:
Management of the Bulk Earthworks
Silt & Sediment Control generally
Safe Vehicle Access and Egress to and from the site during construction
Due consideration of neighbouring properties and local residents at all times during
construction.
Document: CMP01 Construction Management Plan [Version 2.0] Scheduled Review Date: 30/10/2024
Page 6 of 18 qldBUILT Pty Ltd | Uncontrolled when printed Date Reviewed: Xx/xx/xx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.