Construction Management Plan
3.0 Proposed Construction Methodology
3.1 Hours of Work
General construction works will be undertaken within the hours permitted under the development approval.
In some cases, after-hours permits may be sought from the relevant authorities where special
requirements exist, for example oversized deliveries, crane installation and/or demobilization.
Working hours are foreseen as follows:
Between 6:30am – 6:00pm (upon issue of Conditions of consent) - Monday to Friday
Between 6:30am – 6:00pm (upon issue of Conditions of consent) – Saturday
The council will provide further guidance for working times upon Operational Works approval issue.
3.2 Early Works
3.2.1 Dilapidation Survey
Prior to commencing work onsite, a full Pre-Construction Dilapidation Report will be completed. This
detailed survey will encompass visual inspection of structural, architectural, services, conditions of
the existing adjacent neighbouring properties and infrastructure, roads, environment, site
boundaries, Council, Telstra and NBN assets. Access to the adjacent building will be coordinated with
property owners and tenants, at mutually agreed times. A joint inspection with representatives of the
property owners is noted as preferable. It is recommended a post construction survey be compiled
for comparison.
3.2.2 Surveys
A suitably licensed Land Surveyor will be used to set out the works to ensure works are
completed in the correct location and within building tolerance. As-built surveys will be completed
in accordance with Head Contract and authority requirements.
3.2.3 Geotechnical
Further geotechnical advice will be sought as required to carry out testing and inspections as required
by Australian Standards and the Civil Works Specifications. Any geotechnical laboratory carrying out
testing for this project will be NATA accredited.
3.2.4 Service Identification, Connections and Diversions
A desktop “dial-before-you-dig” survey has been completed and an onsite service sweep using
multi- frequency electro-magnetic equipment and dual-frequency ground penetrating radar will be
undertaken. All services will be shown on a drawing and marked on the ground for identification.
3.2.5 Closure and Temporary Diversions
A Draft Traffic Management Strategy has been developed for Council’s review and approval to
encompass both pedestrian and vehicular controls during construction.
Please Refer to Appendix 1 – Draft Traffic Management Strategy (TGS/s)
3.2.6 Power Supply
A combination of generator & existing site power be used temporarily until permanent power is
established.
A new Pad Mount Transformer (PMT) will be installed on site.
Document: CMP01 Construction Management Plan [Version 2.0] Scheduled Review Date: 30/10/2024
Page 7 of 18 qldBUILT Pty Ltd | Uncontrolled when printed Date Reviewed: Xx/xx/xx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
qldBUILT Construction Management Plan - JURA Rev02.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.