Minor Change Existing Approval 132008 478 02 {As Published}
14. For a year in which the rainfall is the median of wetter than average years or the median of
dryer than average years for the locality, the operator of the School shall demonstrate via a
mass water balance approach that the effective hydrologic cycle (i.e. the annual amounts of
surface water runoff and groundwater recharge) of the catchments of the significant gully on
the site will not change by more than 10% from their present condition, taking into
consideration the volumes of water harvested in rainwater tanks and reused for in-house
purposes, that is captured and infiltrated via water sensitive urban design measures and also
the external water imported to the site via the piped potable supply.
15. The Developer is to install water quality control devices generally in accordance with the
Stormwater Management Plan. Detailed staging plans and specifications, based on and
generally in accordance with the Plan are to be prepared and submitted (after consultation
with officers of the Council) with the relevant applications for operational works.
16. The Developer is to complete the drainage works progressively in conjunction with
development of the site and generally in accordance with the approved Stormwater
Management Plan. Detailed drainage plans and specifications, based on and generally in
accordance with the approved Drainage Plan, the EMP and these Conditions, are to be
prepared and submitted (after consultation with officers of the Council) with the relevant
applications for operational works.
17. All drainage works as required by the Drainage Plan are to be provided by the developer at
its own cost.
Vehicle Access
18. Vehicular access to the carparking for Stage 5 of the development shall be via the existing
access driveways constructed as part of the previous stages 1-4.
Car Parking
19. Carparking shall be provided within the site generally as shown on drawing Master Plan &
Site Plan SD-01 ‘St Teresa’s Catholic College Stage 5’ dated February 2008 and prepared
by Onedegree, except as modified herein.
20. A minimum of 148 uncovered carpark spaces shall be provided in total.
21. The new carparking area and driveway shall be designed to comply with the provisions of
AS/NZS 2890.1-2004 for user class 3 with allowance for vehicles to enter and leave the site
in a forward gear and with a minimum head clearance (headroom) at any point of 2.2m.
22. The car park and aisles will be constructed with an asphaltic concrete seal that complies with
Council standards. No gravel-surfaced areas are permitted. The car park will also include
stormwater treatment measures in accordance with the approved Stormwater Management
Report.
23. All carparking shall be kept, maintained and line-marked in a condition fit for use.
24. All staff carpark spaces shall be clearly defined by line marking each space with the words
“Staff Parking Only” and by sign posting each space with a similar wording.
Vegetation Protection & Preservation
25. During construction, all vegetation being retained shall be fenced during construction to
ensure trees are not damaged.
26. All underground services, drainage, footpaths, bikepaths, roads and other site works shall
be located to minimize adverse impacts on retained vegetation, particularly their root
systems. This will also require the location of the site office and the materials storage area
to be agreed with by Council’s Construction Technical Officer Development.
Page 5 of 13
Document Set ID: 21473277
Version: 5, Version Date: 18/05/2021