STORMWATER QUALITY
4.1 CONSTRUCTION PHASE STORMWATER QUALITY MANAGEMENT
4.1.1 INTRODUCTION
This section provides conceptual stormwater quality management strategies for construction phase.
These strategies are applicable for all stages of the development. No modelling has been undertaken
for the construction phase stormwater quality management. Detailed Erosion and Sediment Control
Plans will be prepared during detailed design phase and implemented during construction.
4.1.2 POLLUTANTS
Typical pollutants generated during the construction phase of an urban development are shown in
Table 12. These based on Table C4.1 BCC’s Subdivision & Development Guidelines Part C Section 4.1.1
(2008).
Table 12 – Construction Phase Pollutants
Pollutant Potential Source
Litter Paper, construction packaging, food packaging, cement bags, off-cuts.
Sediment Unprotected exposed soils and stockpiles during earthworks and building works.
Hydrocarbons Fuel/oil spills, leaks from construction equipment, and temporary car park areas.
Toxic
Cement Slurry, asphalt primer, solvents, cleaning agents, and washwaters etc.
Materials
pH altering
Cement slurry, acid sulfate soils, and washwaters
substances
4.1.3 WATER QUALITY OBJECTIVES
It is recommended that the amount of runoff crossing and leaving the site is kept to a minimum during
the construction phase to restrict soil erosion and mobilisation of sediments and pollutants through
and off the site. Table 13 presents an extract from Table A, Appendix 2 of the State Planning Policy
(2017) objectives for construction phase stormwater quality management
Table 13 – Construction Phase Performance Criteria
Issue Desired Outcomes
1. Stage clearing and construction works to minimise the area of exposed soil
at any one time.
2. Effectively cover or stabilise exposed soils prior to predicted rainfall.
Erosion control
3. Prior to completion of works for the development, and prior to removal of
sediment controls, all site surfaces must be effectively stabilised using
methods which will achieve effective short-term stabilisation.
1. Direct runoff from exposed site soils to sediment controls that are
appropriate to the extent of disturbance and level of erosion risk.
2. All exposed areas greater than 2500m² must be provided with sediment
Sediment
controls which are designed, implemented and maintained to a standard
Control
which would achieve at least 80% of the average annual runoff volume of
the contributing catchment treated (i.e. 80% hydrological effectiveness) to
50mg/L Total Suspended Solids (TSS) or less, and pH in the range (6.5–8.5).
SITE BASED STORMWATER MANAGEMENT PLAN – Revision B 36 & 38 DUKE STREET, SUNSHINE BEACH
P a g e | 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.