Meeting minutes
GENERAL COMMITTEE MEETING | 9 JUNE 2026
For: Cr Brian Stockwell, Cr Karen Finzel, Cr Amelia Lorentson, Cr
Jessica Phillips, Cr Tom Wegener, Cr Nicola Wilson
Against: None
Amendment No. 3
Moved: Cr Jessica Phillips
Seconded: Cr Amelia Lorentson
That Item D be amended to read:
D. Support the development of an “Active Street” and “Coastal Pathway” awareness
and education campaign across the shire. to raise awareness of the safety and active
transport benefits associated with Active Streets and the ultimate delivery of the
Noosa Cycling and Walking Strategy and Noosa Transport Strategy. Any
implementation of the campaign must be subject to formal endorsement by the
Department of Transport and Main Roads (TMR) and the Queensland Police Service
(QPS), including confirmation that the proposed messaging, signage, and
enforcement approach align with relevant legislation and road safety requirements.
Carried.
For: Cr Brian Stockwell, Cr Karen Finzel, Cr Amelia Lorentson, Cr
Jessica Phillips, Cr Tom Wegener, Cr Nicola Wilson
Against: None
Motion
Moved: Cr Brian Stockwell
Seconded: Cr Tom Wegener
That Council:
A. Note the report by the Project Officer to the General Committee meeting dated 16
March 2026 regarding the Peregian Beach Active St - Stage 1 project status
including key findings from the community consultation activities and proposed
design amendments;
B. Delegate authority to the CEO to finalise, negotiate and award the construction
contract for the Peregian Beach Active Street – Stage 1 Project, including
approval of all contract variations within the approved project budget, for the
purpose of expediting delivery enabling project completion by the required State
and Federal grant funding timeframes noting that regular updates through the
Capital Works Executive process will be distributed to all Councillors.
C. Note that whilst the project is grant funded, financial reconciliation is not finalised,
with additional costs arising from additional community engagement and project
scope changes;
D. Support the development of an “Active Street” and “Coastal Pathway” awareness
and education campaign across the shire. Any implementation of the campaign
must be subject to formal endorsement by the Department of Transport and Main
Roads (TMR) and the Queensland Police Service (QPS), including confirmation
that the proposed messaging, signage, and enforcement approach align with
relevant legislation and road safety requirements.
E. Support the CEO to submit available grant funding applications for Stage 2 of the
Active Street/Coastal Pathway extension to commence design and construction
as soon as practicably possible.
Lost.