ATTACHMENT 1




 Page 18 of 37

OPERATIONAL PLAN 2016-17 PROGRESS REPORT                                                                                                                                                                            ATTACHMENT 1
WORKING IN PARTNERSHIP WITH OUR COMMUNITY
No. Project                                                          Responsibility                                 Te)                                                                                                              SETS
1    Electric Bus trial in conjunction with Translink                Director Planning & Infrastructure           Electric bus trial cancelled due to concerns about whether the trial could be successfully undertaken from an  Completed    8
                                                                                                                  operational perspective.
2    Implementation of Local Economic Plan                           Senior Economic Development Officer          Delivered  innovation programs,  Noosa Connect event,     business information  publications, supported      On track as a  8
                                                                                                                  establishment of Innovate Noosa and tendered for Management services for the Peregian Beach Digital Hub.        multi year
                                                                                                                  On going and extensive client management.                                                                          project
3.   Implementation of Social Strategy                               Community Development Coordinator            12 month review being reported to Council in July 2017. Progress of key initiatives include:                 On track as a  @
                                                                                                                  - Sport and Active Recreation Plan - Draft completed, available for public consultation once endorsed by        multi year
                                                                                                                 Council;                                                                                                            project
                                                                                                                  - Funding for Difficult to Locate Sports Plan sourced (study will be a partnership with Gympie, Sunshine Coast
                                                                                                                  Councils and State Government);
                                                                                                                  - Arts and Culture Plan - Consultation phase underway by Libraries and Galleries;
                                                                                                                  - Volunteers - A ‘Changing Face of Volunteering’ Forum was held in National Volunteers Week;
                                                                                                                  - Grow Your Arts - Quarterly newsletter now in place;
                                                                                                                  - Strategic Planning - one-on-one sessions held with 6 community groups;
                                                                                                                  - Heart Week - first aid training provided to 60 volunteers;
                                                                                                                  - Johns Landing - Community Roundtable established, Land purchased, Stephen Kelly appointed as project
                                                                                                                  officer;
                                                                                                                  - Noosa Youth Network and Northern Sunshine Coast Network formed and functioning; and
                                                                                                                  - Tait Duke Community Cottage officially opened and leased signed with Rotary Club of Noosa Heads.
4    Implementation of Transport Strategy                            Infrastructure Planning & Design Manager     Transport Strategy and Transport Policy adopted by Council on 15 June 2017. Implementation phase has           Completed    eo
                                                                                                                  commenced.
5    Implementation of Waste Reduction and Recycling Plan            Waste & Environmental Health Manager         Significant media coverage and new initiatives have been commenced, many of which are ongoing after the        Completed    @
                                                                                                                  finalisation of the Waste Management Contract. Council has been advised that staff will be pursuing a
                                                                                                                  composting approval to facilitate addition of food waste to the garden waste bins after they are rolled out in
                                                                                                                  September 2017.
6    Waterways Protection - Inspection and Education Program         Waste & Environmental Health Manager         Investigation of over 130 premises through out the Shire shows that a large percentage were deficient in       Completed    @
                                                                                                                  compliance with the Environmental Protection Act. A report on the findings has been compiled and is tabled for
                                                                                                                  presentation in the July round of Council meetings.

SETTING POLICY AND STRATEGY
No. Project                                                          Responsibility                               ee)                                                                                                                ETE
1    Development of new Corporate Plan                               Chief Executive Officer                      Corporate Plan adopted by Council in January 2017.                                                             Completed    @
2    Development of new Planning Scheme                              Planning Scheme Project Manager              Drafting of the new Plan has been the priority for 3 Strategic Planners and is progressing well. Several     On track as a  8
                                                                                                                  projects continue though these are declining in number.                                                         multi year
                                                                                                                  - Car parking study procurement process commencing.                                                                project
                                                                                                                  - Urban design consultants (Tract) have been commissioned, including a local architect.
                                                                                                                  - Councillor workshops continue.
                                                                                                                  - Community engagement was focused on the Business Advisory Group and Professional Advisory Group with
                                                                                                                  individual meetings scheduled with some groups.
3    Development of Digital Transformation Strategy                  Chief Executive Officer                      An organisational Digital Strategy has been developed.                                                         Completed    @
4    Implementation of Heritage Levy Strategy                        Director Community Services                  - Third heritage reference group meeting held in June 2017.                                                  On track asa   @
                                                                                                                  - "Wake up Sunshine" Social History exhibition to celebrate the 50th anniversary of the naming of the Sunshine  multi year
                                                                                                                  Coast opened 15 June 2017.                                                                                         project
                                                                                                                  - Tait Duke Cottage restoration works completed with an official opening on 7 June 2017.
                                                                                                                  - Restoration works on the Boiler House at the Lower Mill Site Cooroy completed
5    Management of Noosa River                                       Environment Officer (Rivers & Coast)         A meeting has been held with the State Government to further Council's position. The Noosa River Plan is     On track as a  @
                                                                                                                  being reviewed and updated. The old River Plan actions have now been reviewed and the new River Plan is         multi year
                                                                                                                  being drafted, along with a Project Plan.                                                                          project

                                                                                                                                                                                                                       Page 18 of 37
Log in to download the original file

2017-07-17 General Committee Agenda(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.