State code 1: Development in a state-controlled road
environment
Table 1.2.1: Development in a state-controlled road environment
 Performance outcomes                                 Acceptable outcomes                                  Response
 Buildings and structures
 PO1 The location of buildings, structures,           AO1.1 Buildings, structures, infrastructure,         Complies with AO – Only awnings
 infrastructure, services and utilities does not      services and utilities are not located in a state-   proposed over footpaths and will not create
 create a safety hazard in a state-controlled road,   controlled road.                                     a safety hazard.
 or cause damage to, or obstruct road transport       AND
 infrastructure                                       AO1.2 Buildings, structures, infrastructure,         Complies with AO - Access arrangements
                                                      services and utilities can be maintained without     improved to State road.
                                                      requiring access to a state-controlled road.
 PO2 The design and construction of Buildings         AO2.1 Facades of buildings and structures            Able to comply with AO
 and structures does not create a safety hazard       facing a state-controlled road are made of non-
 by distracting users of a state-controlled road.     reflective materials.
                                                      OR
                                                      AO2.2 Facades of buildings and structures do         Able to comply with AO
                                                      not reflect point light sources into the face of
                                                      oncoming traffic on a state-controlled road.
                                                      AND
                                                      AO2.3 External lighting of buildings and             Able to comply with AO
                                                      structures is not directed into the face of
                                                      oncoming traffic on a state-controlled road and
                                                      does not involve flashing or laser lights.
                                                      AND
                                                      AO2.4 Advertising devices visible from a state-      Able to comply with AO
                                                      controlled road are located and designed in
                                                      accordance with the Roadside advertising guide,
                                                      Department of Transport and Main Roads, 2013.
 Filling, excavation and retaining structures
 PO4 Filling and excavation does not interfere        No acceptable outcome is prescribed.                 Complies with AO – No earthworks in road.
 with, or result in damage to, infrastructure or
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                       Page 1 of 19
Log in to download the original file

Att 3 - SDAP compliance.pdf · 174 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 18 pages

Page 2

 Performance outcomes                                       Acceptable outcomes                    Response
 services in a state-controlled road.

 Note: Information on the location of services and
 public utility plants in a state-controlled road can be
 obtained from the Dial Before You Dig service.

 Where development will impact on an existing or
 future service or public utility plant in a state-
 controlled road such that the service or public utility
 plant will need to be relocated, the alternative
 alignment must comply with the standards and design
 specifications of the relevant service or public utility
 provider, and any costs of relocation are to be borne
 by the developer.
 PO5 Filling, excavation, building foundations and          No acceptable outcome is prescribed.   Complies with AO – Only minor earthworks
 retaining structures do not undermine, or cause                                                   in road reserve associated with proposed
 subsidence of, a state-controlled road.                                                           awnings.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended an RPEQ
 certified geotechnical assessment, prepared in
 accordance with Volume 3 of the Road Planning And
 Design Manual 2nd edition, Department of Transport
 and Main Roads, 2016, is provided.
 PO6 Filling, excavation, building foundations and          No acceptable outcome is prescribed.   Complies with AO – Only minor earthworks
 retaining structures do not cause ground water                                                    in road reserve associated with proposed
 disturbance in a state-controlled road.                                                           awnings.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended an RPEQ
 certified geotechnical assessment, prepared in
 accordance with Volume 3 of the Road planning and
 design manual 2nd edition, Department of Transport
 and Main Roads, 2016, is provided.
 PO7 Excavation, boring, piling, blasting or fill           No acceptable outcome is prescribed.   Complies with AO – No substantial
 compaction during construction of a                                                               earthworks required.
 development does not result in ground

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                              Page 2 of 19

Page 3

 Performance outcomes                                  Acceptable outcomes                                    Response
 movement or vibration impacts that would cause
 damage or nuisance to a state-controlled road,
 road transport infrastructure or road works.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended an RPEQ
 certified geotechnical assessment, prepared in
 accordance with Volume 3 of the Road Planning And
 Design Manual 2nd edition, Department of Transport
 and Main Roads, 2016, is provided.
 PO8 Development involving the haulage of fill,        AO8.1 Fill, extracted material and spoil material      Complies with AO – No substantial
 extracted material or excavated spoil material        is not transported to or from the development          earthworks required.
 exceeding 10,000 tonnes per year does not             site on a state-controlled road.
 damage the pavement of a state-controlled road.

 Note: It is recommended a pavement impact
 assessment is provided in accordance with the Guide
 to Traffic Impact Assessment, Department of
 Transport and Main Roads, 2017.
 PO9 Filling and excavation associated with the        No acceptable outcome is prescribed.                   Complies with AO - Access arrangements
 construction of vehicular access to a                                                                        improved to State road.
 development does not compromise the operation
 or capacity of existing drainage infrastructure for
 a state-controlled road.
 PO10 Fill material used on a development site         AO10.1 Fill material is free of contaminants           Complies with AO – No substantial
 does not result in contamination of a state-          including acid sulfate content.                        earthworks required.
 controlled road.
                                                       Note: Soils and rocks should be tested in accordance
                                                       with AS 1289.0 – Methods of testing soils for
                                                       engineering purposes and AS 4133.0-2005 –
                                                       Methods of testing rocks for engineering purposes.
                                                       AND
                                                       AO10.2 Compaction of fill is carried out in            Complies with AO – No substantial
                                                       accordance with the requirements of AS 1289.0          earthworks required.
                                                       2000 – Methods of testing soils for engineering
                                                       purposes.

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                         Page 3 of 19

Page 4

 Performance outcomes                                Acceptable outcomes                                      Response
 PO11 Filling and excavation does not cause          AO11.1 Compaction of fill is carried out in              Complies with AO – No substantial
 wind-blown dust nuisance in a state-controlled      accordance with the requirements of AS 1289.0            earthworks required.
 road.                                               2000 – Methods of testing soils for engineering
                                                     purposes.
                                                     AND
                                                     AO11.2 Dust suppression measures are used                Complies with AO – No substantial
                                                     during filling and excavation activities such as         earthworks required.
                                                     wind breaks or barriers and dampening of
                                                     ground surfaces.
 Stormwater and drainage
 PO12 Development does not result in an              No acceptable outcome is prescribed.                     Complies with AO - Access arrangements
 actionable nuisance, or worsening of,                                                                        improved to State road with associated
 stormwater, flooding or drainage impacts in a                                                                stormwater improved with new curb and
 state-controlled road.                                                                                       channelling to local roads.

 PO13 Run-off from the development site is not       AO13.1 Development does not create any new               Complies with AO - Access arrangements
 unlawfully discharged to a state-controlled road.   points of discharge to a state-controlled road.          improved to State road with associated
                                                     AND                                                      stormwater improved with new curb and
                                                                                                              channelling to local roads.

                                                     AO13.2 Stormwater run-off is discharged to a             Complies with AO - Access arrangements
                                                     lawful point of discharge.                               improved to State road with associated
                                                                                                              stormwater improved with new curb and
                                                     Note: Section 3.4 of the Queensland Urban Drainage       channelling to local roads.
                                                     Manual, Department of Energy and Water Supply,
                                                     2013, provides further information on lawful points of
                                                     discharge.
                                                     AND
                                                     AO13.3 Development does not worsen the                   Complies with AO - Access arrangements
                                                     condition of an existing lawful point of discharge       improved to State road with associated
                                                     to the state-controlled road.                            stormwater improved with new curb and
                                                                                                              channelling to local roads.
 PO14 Run-off from the development site during       AO14.1 Run-off from the development site                 Complies with AO - Access arrangements
 construction does not cause siltation of            during construction is not discharged to                 improved to State road with associated
 stormwater infrastructure affecting a state-        stormwater infrastructure for a state-controlled         stormwater improved with new curb and

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                         Page 4 of 19

Page 5

 Performance outcomes                              Acceptable outcomes                                       Response
 controlled road.                                  road.                                                     channelling to local roads.

 Vehicular access to a state-controlled road
 PO15 Vehicular access to a state-controlled road AO15.1 Development does not require new or                 Complies with AO – Number of accesses
 that is a limited access road is consistent with changed access to a limited access road.                   reduced to nil. Access arrangements
 government policy for the management of limited                                                             improved to State road.
 access roads.                                    Note: Limited access roads are declared by the
                                                   transport chief executive under section 54 of the
                                                   Transport Infrastructure Act 1994 and are identified in
                                                   the DA mapping system.
                                                   OR
                                                   AO15.2 A new or changed access to a limited               Complies with AO – Number of accesses
                                                   access road is consistent with the limited access         reduced to nil. Access arrangements
                                                   policy for the state-controlled road.                     improved to State road.

                                                   Note: Limited access policies for limited access roads
                                                   declared under the Transport Infrastructure Act 1994
                                                   can be obtained by contacting the relevant
                                                   Department of Transport and Main Roads regional
                                                   office.
                                                   AND
                                                   AO15.3 Where a new or changed access is for a             Complies with AO – Number of accesses
                                                   service centre, access is consistent with the             reduced to nil. Access arrangements
                                                   Service centre policy, Department of Transport            improved to State road.
                                                   and Main Roads, 2013 and the Access policy for
                                                   roadside service centre facilities on limited
                                                   access roads, Department of Transport and Main
                                                   Roads, 2013, and the Service centre strategy for
                                                   the state-controlled road.

                                                   Note: The Service centre policy, Department of
                                                   Transport and Main Roads, 2013, Access policy for
                                                   roadside service centre facilities, Department of
                                                   Transport and Main Roads, 2013 and the relevant
                                                   Service centre strategy for a state-controlled road can
                                                   be accessed by contacting the relevant Department of

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                           Page 5 of 19

Page 6

 Performance outcomes                                    Acceptable outcomes                                       Response
                                                         Transport and Main Roads regional office.
 PO16 The location and design of vehicular               AO16.1 Vehicular access is provided from a                Complies with AO – Number of accesses
 access to a state-controlled road (including            local government road.                                    reduced to nil. Access arrangements
 access to a limited access road) does not create                                                                  improved to State road.
 a safety hazard for users of a state-controlled
 road or result in a worsening of operating              OR all of the following acceptable outcomes               Complies with AO – Number of accesses
 conditions on a state-controlled road.                  apply:                                                    reduced to nil. Access arrangements
                                                                                                                   improved to State road.
 Note: Where a new or changed access between the         AO16.2 Vehicular access for the development is
 premises and a state-controlled road is proposed, the   consistent with the function and design of the
 Department of Transport and Main Roads will need to     state-controlled road.
 assess the proposal to determine if the vehicular       AND
 access for the development is safe. An assessment
 can be made by Department of Transport and Main         AO16.3 Development does not require new or                Complies with AO – Number of accesses
 Roads as part of the development assessment             changed access between the premises and the               reduced to nil. Access arrangements
 process and a decision under section 62 of Transport    state-controlled road.                                    improved to State road.
 Infrastructure Act 1994 issued where sufficient
 information is provided.                                Note: A decision under section 62 of the Transport
                                                         Infrastructure Act 1994 outlines the approved
                                                         conditions for use of an existing vehicular access to a
                                                         state-controlled road. Current section 62 decisions
                                                         can be obtained from the relevant Department of
                                                         Transport and Main Roads regional office.
                                                         AND
                                                         AO16.4 Use of any existing vehicular access to            Complies with AO – Number of accesses
                                                         the development is consistent with a decision             reduced to nil. Access arrangements
                                                         under section 62 of the Transport Infrastructure          improved to State road.
                                                         Act 1994.

                                                         Note: The development which is the subject of the
                                                         application must be of an equivalent use and intensity
                                                         for which the section 62 approval was issued and the
                                                         section 62 approval must have been granted no more
                                                         than 5 years prior to the lodgement of the application.
                                                         AND
                                                         AO16.5 Onsite vehicle circulation is designed to          Complies with AO – Number of accesses
                                                         give priority to entering vehicles at all times so        reduced to nil. Access arrangements
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                             Page 6 of 19

Page 7

 Performance outcomes                               Acceptable outcomes                                  Response
                                                    vehicles do not queue in a road intersection or      improved to State road.
                                                    on the state-controlled road.
 PO17 Vehicular access to a state-controlled road AO17.1 Vehicular access and associated road            Complies with AO – Access to the State
 or local government road (and associated road      access works are not located within 5 metres of      road to be removed and not interfere with
 access works) are located and designed to not      existing public passenger transport                  bus stop infrastructure.
 damage or interfere with public passenger          infrastructure.
 transport infrastructure, public passenger         AND
 services or pedestrian or cycle access to public   AO17.2 The location and design of vehicular          Complies with AO – Access to the State
 passenger transport infrastructure and public      access for a development does not necessitate        road to be removed and not interfere with
 passenger services.                                the relocation of existing public passenger          bus stop infrastructure.
                                                    transport infrastructure.
                                                    AND
                                                    AO17.3 On-site vehicle circulation is designed to    Complies with AO – Access to the State
                                                    give priority to entering vehicles at all times so   road to be removed and not interfere with
                                                    vehicles using a vehicular access do not obstruct    bus stop infrastructure.
                                                    public passenger transport infrastructure and
                                                    public passenger services or obstruct pedestrian
                                                    or cycle access to public passenger transport
                                                    infrastructure and public passenger services.
                                                    AND
                                                    AO17.4 The normal operation of public                Complies with AO – Access to the State
                                                    passenger transport infrastructure or public         road to be removed and not interfere with
                                                    passenger services is not interrupted during         bus stop infrastructure.
                                                    construction of the development.
 Vehicular access to local roads within 100 metres of an intersection with a state-controlled road
 PO18 The location and design of vehicular          AO18.1 Vehicular access is located as far as         Complies with AO – Access located as far
 access to a local road within 100 metres of an     possible from the state-controlled road              as possible from the State road along Opal
 intersection with a state-controlled road does not intersection.                                        Street.
 create a safety hazard for users of a state-       AND
 controlled road.                                   AO18.2 Vehicular access is in accordance with        Complies with AO
                                                    volume 3, parts, 3, 4 and 4A of the Road
                                                    Planning And Design Manual, 2nd edition,
                                                    Department of Transport and Main Roads, 2016.
                                                    AND
                                                    AO18.3 Onsite vehicle circulation is designed to     Complies with AO
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                     Page 7 of 19

Page 8

 Performance outcomes                           Acceptable outcomes                                     Response
                                                give priority to entering vehicles at all times so
                                                vehicles do not queue in the intersection or on
                                                the state-controlled road.
 Planned upgrades
 PO19 Development does not impede delivery of   AO19.1 Development is not located on land               Complies with AO – No planned upgrades
 planned upgrades of state-controlled roads.    identified by the Department of Transport and           for this intersection identified on mapping.
                                                Main Roads as land required for the planned
                                                upgrade of a state-controlled road.

                                                Note: Land required for the planned upgrade of a
                                                state-controlled road is identified in the DA mapping
                                                system.
                                                OR
                                                AO19.2 Development is sited and designed so             Complies with AO
                                                that permanent buildings, structures,
                                                infrastructure, services or utilities are not located
                                                on land identified by the Department of Transport
                                                and Main Roads as land required for the planned
                                                upgrade of a state-controlled road.
                                                OR all of the following acceptable outcomes             Complies with AO
                                                apply:

                                                AO19.3 Structures and infrastructure located on
                                                land identified by the Department of Transport
                                                and Main Roads as land required for the planned
                                                upgrade of a state-controlled road are able to be
                                                readily relocated or removed without materially
                                                affecting the viability or functionality of the
                                                development.
                                                AND
                                                AO19.4 Vehicular access for the development is          Complies with AO
                                                consistent with the function and design of the
                                                planned upgrade of the state-controlled road.
                                                AND
                                                AO19.5 Development does not involve filling and         Complies with AO

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                      Page 8 of 19

Page 9

 Performance outcomes                                    Acceptable outcomes                                   Response
                                                         excavation of, or material changes to, land
                                                         required for a planned upgrade to a state-
                                                         controlled road.
                                                         AND
                                                         AO19.6 Land is able to be reinstated to the pre-      Complies with AO
                                                         development condition at the completion of the
                                                         use.
 Network impacts
 PO20 Development does not result in a                   No acceptable outcome is prescribed.                  Complies with AO
 worsening of operating conditions on the state-
 controlled road network.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended that an
 RPEQ certified traffic impact assessment is provided,
 prepared in accordance with the Guide to Traffic
 Impact Assessment, Department of Transport and
 Main Roads, 2017.
 PO21 Development does not impose traffic                AO21.1 The layout and design of the                   Complies with AO – no new accesses to
 loadings on a state-controlled road which could         development directs traffic generated by the          State road and directs traffic to local road.
 be accommodated on the local road network.              development to the local road network.
 PO22 Upgrade works on, or associated with, a            AO22.1 Upgrade works required as a result of          Complies with AO
 state-controlled road are built in accordance with      the development are designed and constructed
 Queensland road design standards.                       in accordance with the Road planning and
                                                         design manual, 2nd edition, Department of
                                                         Transport and Main Roads, 2016.

                                                         Note: Road works in a state-controlled road require
                                                         approval under section 33 of the Transport
                                                         Infrastructure Act 1994 before the works commence.



Table 1.2.2: Environmental emissions
 Performance outcomes                                    Acceptable outcomes                                   Response
 Noise

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                              Page 9 of 19

Page 10

 Performance outcomes                                Acceptable outcomes                                         Response
 Accommodation activities
 PO23 Development involving an accommodation         AO23.1 A noise barrier or earth mound is                    Complies with AO – residential buildings
 activity or land for a future accommodation         provided which is designed, sited and                       orientated away from main road and can be
 activity minimises noise intrusion from a state-    constructed:                                                finished with materials for noise attenuation.
 controlled road or type 1 multi-modal corridor in   1. to meet the following external noise criteria at
 habitable rooms.                                       all facades of the building envelope:
                                                        a. ≤60 dB(A) L 10 (18 hour) façade corrected
                                                             (measured L 90 (8 hour) free field between
                                                             10pm and 6am ≤40 dB(A))
                                                        b. ≤63 dB(A) L 10 (18 hour) façade corrected
                                                             (measured L 90 (8 hour) free field between
                                                             10pm and 6am >40 dB(A))
                                                     2. in accordance with chapter 7 integrated noise
                                                        barrier design of the Transport Noise
                                                        Management Code of Practice – Volume 1
                                                        Road Traffic Noise, Department of Transport
                                                        and Main Roads, 2013.

                                                     Note: To demonstrate compliance with the acceptable
                                                     outcome, it is recommended that a RPEQ certified
                                                     noise assessment report is provided, prepared in
                                                     accordance with the State Development Assessment
                                                     Provisions Supporting Information – Community
                                                     Amenity (Noise), Department of Transport and Main
                                                     Roads, 2013.

                                                     If the building envelope is unknown, the deemed-to-
                                                     comply setback distances for buildings stipulated by
                                                     the local planning instrument or relevant building
                                                     regulations should be used.

                                                     In some instances the design of noise barriers and
                                                     mounds to achieve the noise criteria above the
                                                     ground floor may not be reasonable or practicable. In
                                                     these instances, any relaxation of the criteria is at the
                                                     discretion of the Department of Transport and Main
                                                     Roads.
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                               Page 10 of 19

Page 11

 Performance outcomes                          Acceptable outcomes                                    Response
                                               OR all of the following acceptable outcomes
                                               apply:

                                               AO23.2 Buildings which include a habitable room
                                               are setback the maximum distance possible from
                                               a state-controlled road or type 1 multi-modal
                                               corridor.
                                               AND
                                               AO23.3 Buildings are designed and oriented so          Complies with AO – residential buildings
                                               that habitable rooms are located furthest from a       orientated away from main road and can be
                                               state-controlled road or type 1 multi-modal            finished with materials for noise attenuation.
                                               corridor.
                                               AND
                                               AO23.4 Buildings (other than a relevant                Complies with AO – residential buildings
                                               residential building or relocated building) are        orientated away from main road and can be
                                               designed and constructed using materials which         finished with materials for noise attenuation.
                                               ensure that habitable rooms meet the following
                                               internal noise criteria:
                                               1. ≤35 dB(A) Leq (1 hour) (maximum hour over
                                                   24 hours).

                                               Statutory note: Noise levels from a state-controlled
                                               road or type 1 multi-modal corridor are to be
                                               measured in accordance with AS1055.1–1997
                                               Acoustics – Description and measurement of
                                               environmental noise.

                                               Note: To demonstrate compliance with the acceptable
                                               outcome, it is recommended that a RPEQ certified
                                               noise assessment report is provided, prepared in
                                               accordance with the State Development Assessment
                                               Provisions Supporting Information – Community
                                               Amenity (Noise), Department of Transport and Main
                                               Roads, 2013.

                                               Habitable rooms of relevant residential buildings

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                    Page 11 of 19

Page 12

 Performance outcomes                                Acceptable outcomes                                     Response
                                                     located within a transport noise corridor must comply
                                                     with the Queensland Development Code MP4.4
                                                     Buildings in a transport noise corridor, Queensland
                                                     Government, 2015. Transport noise corridors are
                                                     mapped on the DA mapping system.
 PO24 Development involving an accommodation         AO24.1 A noise barrier or earth mound is                Complies with AO – residential buildings
 activity or land for a future accommodation         provided which is designed, sited and                   orientated away from main road and can be
 activity minimises noise intrusion from a state-    constructed:                                            finished with materials for noise attenuation.
 controlled road or type 1 multi-modal corridor in   1. to meet the following external noise criteria in
 outdoor spaces for passive recreation.                 outdoor spaces for passive recreation:
                                                        a. ≤57 dB(A) L 10 (18 hour) free field
                                                            (measured L 90 (18 hour) free field
                                                            between 6am and 12 midnight ≤45
                                                            dB(A))
                                                        b. ≤60 dB(A) L 10 (18 hour) free field
                                                            (measured L 90 (18 hour) free field
                                                            between 6am and 12 midnight >45
                                                            dB(A))
                                                     2. in accordance with chapter 7 integrated noise
                                                        barrier design of the Transport Noise
                                                        Management Code of Practice – Volume 1
                                                        Road Traffic Noise, Department of Transport
                                                        and Main Roads, 2013.

                                                     Note: To demonstrate compliance with the acceptable
                                                     outcome, it is recommended that a RPEQ certified
                                                     noise assessment report is provided, prepared in
                                                     accordance with the State Development Assessment
                                                     Provisions Supporting Information – Community
                                                     Amenity (Noise), Department of Transport and Main
                                                     Roads, 2013.
                                                     OR
                                                     AO24.2 Each dwelling has access to an outdoor           Complies with AO – residential buildings
                                                     space for passive recreation which is shielded          orientated away from main road and can be
                                                     from a state-controlled road or type 1 multi-           finished with materials for noise attenuation.
                                                     modal corridor by a building, solid gap-free

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                           Page 12 of 19

Page 13

 Performance outcomes                                Acceptable outcomes                                    Response
                                                     fence, or other solid gap-free structure.
                                                     AND
                                                     AO24.3 Each dwelling with a balcony directly           Complies with AO – residential buildings
                                                     exposed to noise from a state-controlled road or       orientated away from main road and can be
                                                     type 1 multi-modal corridor has a continuous           finished with materials for noise attenuation.
                                                     solid gap-free balustrade (other than gaps
                                                     required for drainage purposes to comply with
                                                     the Building Code of Australia).
 Child care centres
 PO25 Development involving a:                       AO25.1 A noise barrier or earth mound is               N/A
 1. child care centre; or                            provided which is designed, sited and
 2. educational establishment                        constructed:
 minimises noise intrusion from a state-controlled   1. to meet the following external noise criteria at
 road or type 1 multi-modal corridor in indoor          all facades of the building envelope:
 education areas and indoor play areas.                 a. ≤58 dB(A) L 10 (1 hour) façade corrected
                                                             (maximum hour during normal opening
                                                             hours)
                                                     2. in accordance with chapter 7 integrated noise
                                                        barrier design of the Transport Noise
                                                        Management Code of Practice – Volume 1
                                                        Road Traffic Noise, Department of Transport
                                                        and Main Roads, 2013.

                                                     Note: To demonstrate compliance with the acceptable
                                                     outcome, it is recommended that a RPEQ certified
                                                     noise assessment report is provided, prepared in
                                                     accordance with the State Development Assessment
                                                     Provisions Supporting Information – Community
                                                     Amenity (Noise), Department of Transport and Main
                                                     Roads, 2013.

                                                     If the building envelope is unknown, the deemed-to-
                                                     comply setback distances for buildings stipulated by
                                                     the local planning instrument or relevant building
                                                     regulations should be used.
                                                     OR all of the following acceptable outcomes            N/A
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                          Page 13 of 19

Page 14

 Performance outcomes                          Acceptable outcomes                                    Response
                                               apply:

                                               AO25.2 Buildings which include indoor education
                                               areas and indoor play areas are setback the
                                               maximum distance possible from a state-
                                               controlled road or type 1 multi-modal corridor.
                                               AND
                                               AO25.3 Buildings are designed and oriented so          N/A
                                               that indoor
                                               education areas and indoor play areas are
                                               located furthest from the state-controlled road or
                                               type 1 multi-modal corridor.
                                               AND
                                               AO25.4 Buildings are designed and constructed          N/A
                                               using materials which ensure indoor education
                                               areas and indoor play areas meet the following
                                               internal noise criteria:
                                               1. ≤35 dB(A) Leq (1 hour) (maximum hour
                                                   during opening hours).

                                               Statutory note: Noise levels from a state-controlled
                                               road or type 1 multi-modal corridor are to be
                                               measured in accordance with AS1055.1–1997
                                               Acoustics – Description and measurement of
                                               environmental noise.

                                               Note: To demonstrate compliance with the acceptable
                                               outcome, it is recommended that a RPEQ certified
                                               noise assessment report, prepared in accordance
                                               with the State Development Assessment Provisions
                                               Supporting Information – Community Amenity (Noise),
                                               Department of Transport and Main Roads, 2013, is
                                               provided.
 PO26 Development involving a:                 AO26.1 A noise barrier or earth mound is               N/A
 1. child care centre; or                      provided which is designed, sited and
 2. educational establishment                  constructed:

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                 Page 14 of 19

Page 15

 Performance outcomes                                Acceptable outcomes                                    Response
 minimises noise intrusion from a state-controlled   1. to meet the following external noise criteria in
 road or type 1 multi-modal corridor in outdoor         each outdoor education area or outdoor play
 education areas and outdoor play areas.                area:
                                                        a. ≤63 dB(A) L 10 (12 hour) free field
                                                            (between 6am and 6pm)
                                                     2. in accordance with chapter 7 integrated noise
                                                        barrier design of the Transport Noise
                                                        Management Code of Practice – Volume 1
                                                        Road Traffic Noise, Department of Transport
                                                        and Main Roads, 2013.

                                                     Note: To demonstrate compliance with the acceptable
                                                     outcome, it is recommended that a RPEQ certified
                                                     noise assessment report is provided, prepared in
                                                     accordance with the State Development Assessment
                                                     Provisions Supporting Information – Community
                                                     Amenity (Noise), Department of Transport and Main
                                                     Roads, 2013.
                                                     OR
                                                     AO26.2 Each outdoor education area and                 N/A
                                                     outdoor play area is shielded from noise
                                                     generated from a state-controlled road or type 1
                                                     multi-modal corridor by a building, solid gap-free
                                                     fence, or other solid gap-free structure.
 Hospitals
 PO27 Development involving a hospital               AO27.1 Hospitals are designed and constructed          N/A
 minimises noise intrusion from a state-controlled   using materials which ensure patient care areas
 road or type 1 multi-modal corridor in patient      meet the following internal noise criteria:
 care areas.                                         1. ≤35 dB(A) Leq (1 hour) (maximum hour
                                                         during opening hours).

                                                     Statutory note: Noise levels from a state-controlled
                                                     road or type 1 multi-modal corridor are to be
                                                     measured in accordance with AS1055.1–1997
                                                     Acoustics – Description and measurement of
                                                     environmental noise.

State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                       Page 15 of 19

Page 16

 Performance outcomes                                 Acceptable outcomes                                   Response
                                                      Note: To demonstrate compliance with the acceptable
                                                      outcome, it is recommended that a RPEQ certified
                                                      noise assessment report is provided, prepared in
                                                      accordance with the State Development Assessment
                                                      Provisions Supporting Information – Community
                                                      Amenity (Noise), Department of Transport and Main
                                                      Roads, 2013.
 Vibration
 Hospitals
 PO28 Development involving a hospital                AO28.1 Hospitals are designed and constructed         N/A
 minimises vibration impacts from vehicles using      to ensure vibration in the treatment area of a
 a state-controlled road or type 1 multi-modal        patient care area does not exceed a vibration
 corridor in patient care areas.                      dose value of 0.1m/s1.75.
                                                      AND
                                                      AO28.2 Hospitals are designed and constructed         N/A
                                                      to ensure vibration in the ward area of a patient
                                                      care area does not exceed a vibration dose
                                                      value of 0.4m/s1.75.

                                                      Note: To demonstrate compliance with the acceptable
                                                      outcome, it is recommended that a RPEQ certified
                                                      vibration assessment report is provided.
 Air and light
 PO29 Development involving an accommodation          AO29.1 Each dwelling has access to an outdoor         Complies with AO – residential buildings
 activity minimises air quality impacts from a        space for passive recreation which is shielded        orientated away from main road and can be
 state-controlled road or type 1 multi-modal          from a state-controlled road or type 1 multi-         finished with materials for noise attenuation.
 corridor in outdoor spaces for passive recreation.   modal corridor by a building, solid gap-free
                                                      fence, or other solid gap-free structure.
 PO30 Development involving a:                        AO30.1 Each outdoor education area and                Complies with AO – residential buildings
 1. child care centre; or                             outdoor play area is shielded from a state-           orientated away from main road and can be
 2. educational establishment                         controlled road or type 1 multi-modal corridor by     finished with materials for noise atte Complies
 minimises air quality impacts from a state-          a building, solid gap-free fence, or other solid      with AO – residential buildings orientated away
 controlled road or type 1 multi-modal corridor in    gap-free structure.                                   from main road and can be finished with
 outdoor education areas and outdoor play areas.                                                            materials for noise attenuation.nuation.
 PO31 Development involving an accommodation          AO31.1 Buildings for an accommodation activity
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                          Page 16 of 19

Page 17

 Performance outcomes                              Acceptable outcomes                                     Response
 activity or hospital minimises lighting impacts   or hospital are designed to minimise the number
 from a state-controlled road or type 1 multi-     of windows or transparent/translucent panels
 modal corridor.                                   facing a state-controlled road or type 1 multi-
                                                   modal corridor.
                                                   OR
                                                   AO31.2 Windows facing a state-controlled road           Complies with AO – residential buildings
                                                   or type 1 multi-modal corridor include treatments       orientated away from main road and can be
                                                   to block light from a state-controlled road or type     finished with materials for noise attenuation.
                                                   1 multi-modal corridor.


Table 1.2.3: Development in a future state-controlled road environment
 Performance outcomes                              Acceptable outcomes                                     Response
 PO32 Development does not impede delivery of      AO32.1 Development is not located in a future           N/A
 a future state-controlled road.                   state-controlled road.
                                                   OR


                                                   AO32.2 Development is sited and designed so             N/A
                                                   that permanent buildings, structures,
                                                   infrastructure, services or utilities are not located
                                                   in a future state-controlled road.
                                                   OR all of the following acceptable outcomes             N/A
                                                   apply:

                                                   AO32.3 Structures and infrastructure located in a
                                                   future state-controlled road are able to be readily
                                                   relocated or removed without materially affecting
                                                   the viability or functionality of the development.
                                                   AND
                                                   AO32.4 Development does not involve filling and         N/A
                                                   excavation of, or material changes to, a future
                                                   state-controlled road.
                                                   AND
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                                         Page 17 of 19

Page 18

 Performance outcomes                                      Acceptable outcomes                                   Response
                                                           AO32.5 Land is able to be reinstated to the pre-
                                                           development condition at the completion of the
                                                           use.
 PO33 Vehicular access to a future state-                  AO33.1 Development does not require new or            N/A
 controlled road is located and designed to not            changed access between the premises and a
 create a safety hazard for users of a future state-       future state-controlled road.
 controlled road or result in a worsening of               AND
 operating conditions on a future state-controlled         AO33.2 Vehicular access for the development is        N/A
 road.                                                     consistent with the function and design of the
                                                           future state-controlled road.
 Note: Where a new or changed access between the
 premises and a future state-controlled road is
 proposed, the Department of Transport and Main
 Roads will need to assess the proposal to determine
 if the vehicular access for the development is safe. An
 assessment can be made by Department of Transport
 and Main Roads as part of the development
 assessment process and a decision under section 62
 of Transport Infrastructure Act 1994 issued where
 sufficient information is provided.
 PO34 Filling, excavation, building foundations            No acceptable outcome is prescribed.                  N/A
 and retaining structures do not undermine, or
 cause subsidence of, a future state-controlled
 road.

 Note: To demonstrate compliance with this
 performance outcome, it is recommended that an
 RPEQ certified geotechnical assessment is provided,
 prepared in accordance with volume 3 of the Road
 planning and design manual, 2nd edition, Department
 of Transport and Main Roads, 2016.
 PO35 Fill material from a development site does           AO35.1 Fill material is free of contaminants          N/A
 not result in contamination of land for a future          including acid sulfate content.
 state-controlled road.
                                                           Note: Soil and rocks should be tested in accordance
                                                           with AS1289 – Methods of testing soils for
                                                           engineering purposes and AS4133 2005 – Methods of
State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                            Page 18 of 19

Page 19

 Performance outcomes                                 Acceptable outcomes                                      Response
                                                      testing rocks for engineering purposes.
                                                      AND
                                                      AO35.2 Compaction of fill is carried out in              N/A
                                                      accordance with the requirements of AS1289.0
                                                      2000 – Methods of testing soils for engineering
                                                      purposes.
 PO36 Development does not result in an               No acceptable outcome is prescribed.                     N/A
 actionable nuisance, or worsening of,
 stormwater, flooding or drainage impacts in a
 future state-controlled road.
 PO37 Run-off from the development site is not        AO37.1 Development does not create any new               N/A
 unlawfully discharged to a future state-controlled   points of discharge to a future state-controlled
 road.                                                road.
                                                      AND
                                                      AO37.2 Stormwater run-off is discharged to a             N/A
                                                      lawful point of discharge.

                                                      Note: Section 3.4 of the Queensland Urban Drainage
                                                      Manual, Department of Energy and Water Supply,
                                                      2013, provides further information on lawful points of
                                                      discharge.
                                                      AND
                                                      AO37.3 Development does not worsen the                   N/A
                                                      condition of an existing lawful point of discharge
                                                      to the future state-controlled road.




State Development Assessment Provisions – version 2.0
State code 1: Development in a state-controlled road environment                                                          Page 19 of 19

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.