Skip to the record
Noosa’s premier civic archive.

Original source · versioned page text

2019-12-11 SM Agenda - Item 1 - Attachment 4 - Final New Noosa Plan Part 8-9 Schedule Appendix Track Change version

of 195

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (14.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
      Performance outcomes                                            Acceptable Outcomes
            disturbed areas are reinstated and revegetated on
                                                                      Editor’s Note— Measures may include fauna underpasses,
            completion of works; and
                                                                      ropes, fencing and the like.
      (f)   minimise bulk earthworks.
                                                                      AO12.4
                                                                      Road infrastructure within or adjacent to native habitat
                                                                      incorporates fences which allow for protected wildlife
                                                                      movement and controls unrestricted access of domestic cats
                                                                      and dogs.

                                                                      AO12.5
                                                                      Native vegetation is protected from clearing or construction
                                                                      activities by—
                                                                      (a)   clearly marking vegetation to be retained with flagging
                                                                            tape;
                                                                      (b)   installing protective fencing around the dripline of
                                                                            vegetation; and
                                                                      (c)   ensuring stock piling, storage and vehicle parking occur
                                                                            outside the areas of vegetation to be retained.

                                                                      AO12.6
                                                                      Where clearance of habitat is unavoidable, once the area
                                                                      disturbed by the works is re­established, replacement habitat
                                                                      is planted in proximity of the works to create native fauna
                                                                      habitat suitable for the area and maintained for the life of the
                                                                      works.
      PO13                                                            AO13
      Road infrastructure is constructed to minimise adverse          Road infrastructure is constructed in accordance with
      environmental impacts, including from run­off and erosion.      Council’s Planning Scheme Policy PSP6 Engineering Design
                                                                      Standards – Roads, drainage and earthworks




     Table 9.4.8.3 Criteria for assessable development (part)
      Performance outcomes                                            Acceptable Outcomes




     Table 9.4.8.7.3 Criteria for assessable development (part)
      Performance outcomes                                            Acceptable Outcomes
      External Works and Infrastructure
      PO14                                                            AO14
      Development is provided with external works—                    Where not already existing, the following infrastructure
      (a)   along the full extent of the frontage of the site to an   components are provided at the frontage of the site—
            appropriate standard having regard to the specified       (a)   full width sealed road;
            function of the road; and                                 (b)   concrete kerb and channel where appropriate;
      (b)   provided beyond the site’s frontage if required.          (c)   forming and grading to footpaths;
                                                                      (d)   vehicular kerb and footpath crossings;
                                                                      (e)   a constructed bikeway;
                                                                      (f)   a constructed footpath;
                                                                      (g)   a constructed carriageway;
                                                                      (h)   required alterations to public utility mains, services or
                                                                            installations;



**FINAL DRAFT ­ Post Consultation 2019**                                                                                                Page 7 of 8
Log in to download the original file

2019-12-11 SM Agenda - Item 1 - Attachment 4 - Final New Noosa Plan Part 8-9 Schedule Appendix Track Change version(PDF, 14MB).pdf · 14.9 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.