13
Specific Outcomes Solutions
09 The subdivision layout is designed to facilitate Reconfiguration maintains the ability for
linkages with adjoining sites in the immediate further pedestrian linkages to be created
area. in the future if required.
010 Where the lots are to be used for Industrial Not applicable.
business or Commercial business uses, the
layout provides for appropriate buffer areas, to
mitigate possible impacts on nearby residences
or other noise sensitive uses.
011 For lots in the Rural Settlement Zone-a Not applicable.
sealed access to the nearest urban settlement is
available.
Water supply for fire fighting
012 An adequate and accessible water supply is All lots will be connected to a reticulated
provided for fire fighting purposes. water supply that is reliable and conforms
to Council’s Standards.
Energy efficiency
013 The street and lot orientation facilitates the All lots contain sufficient area to allow
construction of energy efficient buildings that orientation of dwellings to maximise solar
respond to the local climate conditions. access.
AND
014 For residential development, the subdivision
design provides for the maximum practicable
number of lots with house site areas that-
a) maximise solar access to the north in
winter;
b) minimise solar access to the east and west
in the summer;
c) maximise access to any prevailing summer
breezes; and
d) minimise exposure to prevailing winter
winds.
Infrastructure
015 Each lot is capable of being serviced by All lots will be connected to power supply,
appropriate levels of- telecommunications services, water
a) water supply; supply and sewerage reticulation. The
b) reticulated sewerage; proposed location of the Lots with
c) stormwater drainage; extensive road frontage allows for them to
d) power supply; and be connected to services from the road
e) telecommunications; with minimal impact on the environment.
AND
016 The design and provision of public services
and utilities, including sewerage, water,
electricity, street lighting and telecommunication
services-
a) meets the needs of users;
b) ensures health, safety and convenience of
the community;
c) protects the natural environmental values
of the site and surrounds, including visual
amenity and native vegetation;
d) are cost effective over their life cycle;
e) minimises adverse impacts to the
environment (including the amenity of the
13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application part 2 Report and plan REC13/0015Related documentApplication case desk ↗
About this file
- File size
- 10.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.