NOOSA COUNCIL IDAS Development Application Decision Notice                                                   7 of 14


Car Parking
44.   Carparking shall be provided within the site generally as shown on drawing number SK.203 as prepared
      by Kidd & Co designers dated October 2006, and as otherwise amended by conditions of this permit.

45.   The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004 for user
      class 1A with allowance for vehicles to enter and leave the site in a forward gear and with a minimum
      head clearance (headroom) at any point of 2.2m.

46.   All carparking shall be kept, maintained and line-marked in a condition fit for use.
Vegetation Protection & Preservation
47.   Vehicular pavements within the drip zone of any of the existing trees on site to be retained shall be
      designed as a pervious pavement (such as grass paving cells or similar), as this will allow water that falls
      on this surface to penetrate to the trees root system. The pavement shall be constructed so as not to
      damage the tree or their root system and in this regard temporary fencing shall be provided around the
      trees during construction to help protect them.
      Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
      pavement and the temporary fencing prior to obtaining a Development Permit for Operational Works.
48.   Where retained trees are located in areas proposed to be filled on site (or are located on neighbouring
      allotments to the actual site to be filled), there will be a need to prevent fill material from being placed on
      the trees root system. To this end the design of the filling works will need to incorporate terracing around
      the tree or a similar means of ensuring that the natural ground level around the trees remains generally
      the same as existing. These measures shall clearly be shown on the plans submitted for Operational
      Works approval and any drainage required to drain these areas shall also be shown on the plans.

49.   All Class 1, Class 2 and Class 3 pest plants declared under the Land Protection (Pest and Stock Route
      Management) Act 2002 are to be controlled on the site prior to Council endorsement of the plan of survey.
      In this context “controlled” shall mean, for class 1 and 2 pests, completely eradicated. For class 3 pests it
      shall mean removal of the plants where they threaten environmentally significant areas of the site such as
      riparian zones and areas of natural vegetation.
      Where class 3 plants are removed as a result of this condition and there is not sufficient natural
      regeneration of native species, the areas shall be replanted with endemic native species so that a
      sustainable natural ecosystem is restored.
      Council’s Conservation Management Supervisor will not inspect the site until 30 days after the weed
      treatment and replanting is complete.
Frontage Works
50.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the Little Cove
      Road frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants &
      Guidelines. Grass shall be couch, free of weeds.

51.   All redundant vehicular crossings to the site shall be removed and replaced by landscaping such as trees
      and grasses in accordance with Council’s Standard specifications prior to the endorsement of the Plan of
      Survey.
Roof Water & Stormwater Drainage
52.   All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
      collected and discharged so there is no net increase in the rate of discharge as a result of the
      development for storm events up to a “1 in 100 year storm”.

53.   Stormwater runoff is to be controlled on site by using a combination of collection and reuse, detention and
      infiltration with excess runoff disposed of on site in such a manner so as to cause no scour or damage to
      the subject site, adjoining properties, existing waterways or any Council property to the reasonable
      satisfaction of the Manager - Land Development.
      A Development Permit for Building Works shall not be granted until a Development Permit for Operational
      Works has been issued in regard to the drainage scheme.
54.   All stormwater drainage shall be designed in accordance with the Noosa Planning Scheme Policy 5 –
      Engineering Design Standards – Roads, Drainage and Earthworks.

55.   All site stormwater drainage shall be by means of a gravity system.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@5008a612\@[email protected]

Used in these records

About this file

File size
63 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

00156A98.001.pdf · 63 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.