Criteria Action Responsibility
trenches, excavations, cut and fill activities. Open earthworks
pose threats to native animal entrapment and should be
backfilled as soon as possible. In some locations, barriers may
be required overnight to eliminate the accidental capture of
animals moving through the site. When trenches are not
backfilled or machinery left onsite overnight, they are to be
inspected at the commencement of each day for trapped or
injured wildlife.
Introduction of Exotic Species Prior to site Site
entry supervisor, site
The movement and transport of machinery, vehicles and
staff and
equipment that are contaminated with weed and seed is a visitors
source of spreading invasive weeds from infested areas to
weed free locations or areas with minimal infestations.
Vehicles and equipment should be free of any introduced or
exotic species.
Relocation and Translocations of Fauna When identified Fauna Catcher
by Fauna Spotter
Where works will result in unacceptable risks to the health and
catcher spotter,
safety of fauna, a range of measures may be used by the Principal
Contractor or
authorised Fauna Spotted Catcher to minimise risks, including
Proponent
nesting boxes and the temporary removal of animals from the
site with the aim of returning animals back to habitat on site at
the completion of risk associated works or compensatory
habitat offsets are to be provided. Appropriate measures are to
be determined by the approved Fauna Spotter Catcher in
consultation with Council.
Post Operational Works
Site Records Submit to the Principal
proponent 2 Contractor
Site records should be maintained and detail the pre-
weeks following
operational works survey, changes to fauna management completion of
operational
practice and any non-compliance actions such as unplanned
works
disturbances to vegetation. Site records would additionally
include an inventory of species encountered during and a
summary of any fauna handling and relevant events.
Contingency measures and adjustments to fauna management for the proposed
development are subject to continual review for improvement and may need to be
considered in the event strategies are ineffective. In this event, the current mitigation
Page 24
Ecological Assessment Report ± 11C Church St Pomona 4568 QLD,
3 March 2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (11c Church St Pomona Ecological Assessment Rev B.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.