CONCLUSIONS
The aboveground rainwater tanks are able to attenuate the runoff concentrations back to
pre-development levels and so the development will not have an impact on the hydrology of
the existing system.
The internal drainage system has been designed to carry the 20% AEP for both the new
shed/hardstand area and the extensions to the church building.